Contract No: HK/2011/07 Wanchai Development Phase II and Sampling, Field Measurement and Testing Work
(Stage 2) Environmental
Permit no. EP-356/2009, Further Evironmental permit nos. fep-01/356/2009,
fep-02/356/2009, FEP-03/356/2009, Fep-04/356/2009 and fep-05/356/2009 Quarterly
Environmental Monitoring
and Audit Report
- DeCember 2011 to February 2012 -
|
CLIENTS: |
|
Civil Engineering and
Development Department and Highways Department |
Lam Geotechnics Limited 11/F Centre Point Wanchai,
H.K. Telephone: (852) 2882-3939 Facsimile: (852) 2882-3331 E-mail: info@lamenviro.com Website: http://www.lamenviro.com |
|
|
|
|
|
CHECKED
by: |
|
                         Raymond Dai Environmental Team Leader |
|
DATE: |
|
29 March 2012 |
1.1    Scope of the Report
1.2    Structure of the Report
2.   Project Background
2.1    Background
2.2    Scope
of the Project and Site Description
2.3    Division of the Project
Responsibility
2.4    Project Organization and Contact
Personnel
2.5    Principle
Work and Activities
3.   Monitoring Requirements
3.1.    Noise Monitoring
3.2.    Air Monitoring
3.3.    Water Quality Monitoring
4.   Monitoring Results
4.1.    Noise Monitoring Results
4.2.    Real Time Noise Monitoring Results
4.3.    Air Monitoring Results
4.4.    Water Monitoring Results
4.5.    Waste Monitoring Results
5.1.    Noise Monitoring
5.2.    Real-time Noise Monitoring
5.3.    Air Monitoring
5.4.    Water Quality Monitoring
5.5.    Site Audit
5.6.    Review
of the Reasons for and the Implications of Non-compliance
5.7.    Summary
of action taken in the event of and follow-up on non-compliance
6.   Complaints, Notification
of Summons and Prosecution
7.   Cumulative Construction
Impact due to the Concurrent Projects.
lIST OF
TABLES
Table I        Principle Work Activities for Contract no. HY/2009/11
Table II       Principle
Work Activities for Contract no. HK/2009/01
Table III       Principle
Work Activities for Contract no. HK/2009/02
Table IV      Principle Work Activities for Contract no. HY/2009/15
Table V       Principle Work Activities for Contract no. HK/2010/06
Table VI      Principle Work Activities
for Contract no. HY/2009/19
Table 2.1      Schedule 2 Designated Projects under this Project
Table 2.2     Details of Individual Contracts under the Project
Table 2.3     Contact Details of Key Personnel
Table 2.4      Principle Work Activities for Contract no. HY/2009/11
Table 2.5      Principle Work Activities for Contract no. HK/2009/01
Table 2.6      Principle Work Activities for Contract no. HK/2009/02
Table 2.7      Principle Work Activities for Contract no. HY/2009/15
Table 2.8      Principle Work Activities for Contract no. HK/2010/06
Table 2.9      Principle
Work Activities for Contract no. HY/2009/19
Table 3.1     Noise
Monitoring Stations
Table 3.2     Real
Time Noise Monitoring Station
Table 3.3     Air
Monitoring Stations
Table 3.4      Marine
Water Quality Stations for Water Quality Monitoring
Table 3.5     Marine
Water Quality Monitoring Frequency and Parameters
Table 3.6      Marine Water Quality
Stations for Enhanced Water Quality Monitoring
Table 3.7      Marine Water Quality
Stations for Additional DO Monitoring
Table 4.1      Noise
Monitoring Stations for Contract no. 
HY/2009/11
Table 4.2      Noise Monitoring
Station for Contract nos. HK/2009/01 and HK/2009/02
Table 4.3      Noise
Monitoring Station for Contract nos. HY/2009/15
Table 4.4      Noise
Monitoring Station for Contract nos. HY/2009/19
Table 4.5     Real
Time Noise Monitoring Station for Contract no. HY/2009/11
Table 4.6     Real
Time Noise Monitoring Station for Contract no. HY/2009/19
Table 4.7     Air Monitoring
Stations for Contract no. HY/2009/11
Table 4.8      Air Monitoring Stations for Contract no. HK/2009/01
Table 4.9      Air Monitoring
Station for Contract no. HK/2009/02
Table 4.10     Air
Monitoring Station for Contract no. HY/2009/15
Table 4.11     Air
Monitoring Station for Contract no. HY/2009/19
Table 4.12    Water
Monitoring Stations for Contract no. 
HY/2009/11
Table 4.13     Water
Monitoring Stations for Contract no. HK/2009/01
Table 4.14     Water
Monitoring Stations for Contract no. HK/2009/02
Table 4.15     Water
Monitoring Stations for Contract no. HK/2010/06
Table 4.16     Water
Monitoring Stations for Contract no. HY/2009/15
Table
4.17     Water Monitoring Stations for
Contract no. HY/2009/19
Table 4.18     Summary of Water Quality Monitoring Exceedances in Reporting
period
Table 4.19    Details
of Waste Disposal for Contract no. HY/2009/11
Table 4.20    Details
of Waste Disposal for Contract no. HK/2009/01
Table 4.21    Details
of Waste Disposal for Contract no. HK/2009/02
Table 4.22    Details
of Waste Disposal for Contract no. HY/2009/15
Table 4.23    Details
of Waste Disposal for Contract no. HK/2010/06
Table 6.1     Cumulative
Statistics on Complaints
Table 6.2     Cumulative
Statistics on Successful Prosecutions
lIST OF FIGUREs
Figure
2.1     Project
Layout
Figure 2.2     Project
Organization Chart
Figure 3.1     Locations
of Environmental Monitoring Stations
lIST OF APPENDIces
Appendix
2.1  Environmental Mitigation
Implementation Schedule
Appendix 3.1  Action and Limit Level
Appendix
4.1  Noise Monitoring Graphical Presentations
Appendix
4.2  Air Quality Monitoring Graphical Presentations
Appendix
4.3  Water Quality Monitoring Graphical Presentations
Appenidx 4.3a  Additional Dissolved Oxygen
Monitoring Results
Appendix 4.4  Real-time Noise Monitoring Results and Graphical Presentations
Appendix 5.1  Event Action Plans
Appendix 6.1  Complaint Log
Appendix 7.1  Construction Programme of
Individual Contracts
Construction Activities for the
Reported Period
Table I     Principle Work Activities for Contract
no. HY/2009/11
December 2011 |
January 2012 |
February 2012 |
Reclamation works;
Geo-textile laying;
Slotted panel
fixing;
Drainage
Construction works;
Installation of berm
blocks;
Concreting the
slopes of Open Channel U;
Construction of
in-situ mass concrete cooping;
Construction of
granite facing stone; and
Construction of
Seawall Type 8 |
The major work
activities for Contract no. HY/2009/11 was confirmed substantial complete by
RSS on 4 January 2012. The construction site was handed over to contractor
HY/2009/19 and the FEP-01/356/2009 was under application of surrender in this
reporting period. |
The major work
activities for Contract no. HY/2009/11 was confirmed substantial complete by
RSS on 4 January 2012. The construction site was handed over to contractor
HY/2009/19 and the FEP-01/356/2009 was under application of surrender in this
reporting period. |
Table II    Principle Work Activities for Contract no.
HK/2009/01
December 2011 |
January 2012 |
February 2012 |
Dredging works
within HKCEC Water Channel from CH190 to CH260 for Type 1 & 2
Sediment was commences and substantially
completed;
Removal of rock
armours from CH150 to CH180 at the North bank of HKCEC Water
Channel was
commenced and substantially completed;
A trial for Type 3
sediment disposal was carried out;
Installation of
sheet pile for cooling water intake at Dome Promenade between
CH120 and CH170;
Installation of
precast RC outfall at Zone B1-3;
Trench excavation
for the 4 nos. of cooling water discharge pipes at B1-3;
Reclamation of
HKCEC3W (up to CH130) within HKCEC Water Channel;
Installation of
cross -harbour water mains nos. B13, A14/B14 and A15/ B15;
Thrust block
construction for A9/B9 and A11/B11 was commenced;
Concrete coating at
flange joint of cross-harbour water mains nos. A7B7/A8B8,
A8B8/A9B9 and
A9B9/A10B10;
Rockfilling and rock
protection to cross-harbour watermains;
Installation of pipe
pile at TST (Land Portion) was commenced and substantially completed;
Grouting works at
TST seafront along the pipe piles
Dredging of Type 2
sediment from CH50 to CH250 for subsequent cross-harbour
watermains
installation off Tsim Sha Tsui;
Mainlaying works at
Zone B1-5B, B1-6, B2-2, B4-2, B4-5, A1-5A, A3-2A, HKCEC,Zone B1-6, B2-2 and B1-5B; Zone A1-5A1 and A3-5B;
Way In/Out, A2-3B
and A5-5;
Coring and Grouting
works for external wall of cooling pumping stations Nos. P4 & P5 at Zone B4-5;
Coring works for
external wall of cooling pumping station No P1 at Zone B4-2;
Heading No. H3,H4, H5, H7 and H13; was substantially completed.
GI duct laying works
at ZoneA4-3A and Zone A4-3B;
Trench excavation,
pipe laying works and chamber construction for a 1000 dia.
watermains (CHF) at |
Dredging works
within HKCEC Water Channel from CH190 to CH260 for Type 3 sediment was
commended.
Removal of rock armours
from CH160 to CH260 at the north bank of HKCEC Water Channel was
substantially completed.
Installation of
sheet pile for cooling water intake at Dome Promenade between CH120 and CH170
was in progress.
Reclamation of
HKCEC3W (up to CH130) within HKCEC Water Channel has been substantially
completed.
Installation of 4
nos. of submersible cooling water discharge pipes at B1-3 was substantially
completed.
Thrust block
construction for A9B9, A11B11, A12B12 and A13B13 were completed.
Concrete coating at
flange at joint of cross-harbour watermains nos. A10B10/A11B11, A11B11/A12B12
and A12B12/A12B13 were completed.
Rockfilling and rock
protection to cross-harbour watermains was currently in progress.
Grouting works at
TST seafront along the pipe pile wall was commenced.
Installation of pipe
pile at TST (Sea Protection) was substantially completed.
Dredging of Type 3
sediment at designated disposal site was carried out.
Mainlaying works at
Zone B1-5B, B1-6, B2-2, A3-2A, A3-5B and were in progress.
Cable ducting works
at Zone B5-2 was commenced.
Mainlaying works and
subsequent reinstatement in Zone B4-5 was completed.
Mainlaying works and
subsequent carriageway reinstatement in Zone A1-5A1, A4-3A,
A4-3B and HKCEC Way
In/Out had been completed.
Mainlaying works and
subsequent carriageway reinstatement in Zone A2-3B and A2-4A was completed.
Coring and grouting
works for external wall of cooling pumping station No. P1 at Zone B4-2 was
completed.
Pipe laying works at
Zone B4-2 was completed and GI ducting works was in progress.
Jacking pit
establishment for pipe laying works by heading method at Zone A1-5A1 has been
completed.
Mainlaying and
chamber construction works at the traffic island neat junction of
Trench excavation,
pipe laying works and chamber construction for a 1000 dis. Warermains (CHF)
at
Trench excavation
and pipe laying works for a 1000 dia. Watermains (CHE) at |
Marine Works
Dredging works
within HKCEC water Channel form CH190 to Ch260 for Type 2 sediment and Type 3 sediment.
Installation of
sheet pile for cooling water intake at Dome Promenade between CH120 and CH170
Reclamation of
HKCEC3W (up to CH140) within HKCEC Water Channel
Seawall
reinstatement and retaining wall construction at Wan Chai Lanfill in Zone
B1-3 Cross-harbour Watermains Installation
Rockfilling and rock
protection to cross-harbour watermains
Grouting works at
TST seafront along the pipe pile wall
Installation of pipe
pile at TST seafront for pre-splitting seawall blocks
Trench excavation
and installation of shoring system along the pipe pile wall at TST seafront
Dredging of Type 3
sediment from CH50 to CH250 for subsequent cross-habour watermains installation
off TST
Dredging works
underneath Avenue of Stars carried by telescopic excavator
Dredging works in
confined water by 9 in 1 barge
1.1.3 Fresh
Watermains, Cooling Watermains and Salt Watermains (On Land)
Mainlaying works at
Zone B1-3, B1-5, B1-6, B2-2, B4-2, B4-4, B5-2, A1-1, A2-3C, A3-4B, A3-5B and
A4-2A, B4-4, A4-2A, A1-1, A1-4A, A2-3C and A3-4B
Mainlaying works and
subsequent carriageway reinstatement in Zone A5-5 and A3-2A
Cable ducting works
along
Heading No. H5, H7, H8 and H13 (mainlaying woks by trenchless method)
Mainlaying and
chamber construction works at the traffic island near junction of Trench excavation, pipe laying works and chamber construction
for a 1000 dia. watermains (CHF and CHE) at |
Table III    Principle Work Activities for Contract no.
HK/2009/02
December 2011 |
January 2012 |
February 2012 |
300mm thick topping
slab together with the make up slab below at northern portion commenced on 30 Nov 2011;
Concreting at Roof
Plinth, lift shaft up to +14.15mPD and Fire Service Pump room up to +14.15mPD of Passenger Terminal Building were completed;
E&M and ABWF of
ELS of Noise Barrier
2 commenced on 29 Nov 2011 and nearly completed.
Casting of
pedestrian pavement above seawall coping Bay 4 to Bay 8 was completed on 13 December 2011;
Casting of the bus
shelter footing at
Precast slab
installation at the existing movable ramp was in progress;
Saw cutting of
existing slabs for the construction NB1 footing was completed;
E&M of P7, P8
& P9
Approximate 50m
cooling water pipe was laid at Harbour Centre,
Jacking pit at
ex-pet garden for the heading construction of cooling mains across
Convention Avenue
commenced;
Approximate 50m
cable duct was laid at
Construction of wash
out chamber at Centre were completed;
Trench excavation
and cooling mains installation along
Installation of PVC
and G.I cable ducts was ongoing at
Installation of
submarine outfall pipe was completed;
Dredging for
submarine outfall pipe was ongoing;
Concreting the Base
Slab of Wan Shing Street at Bay 24 was completed;
Concreting the wall
shaft and roof slab completed of Bay 24 were completed;
Bay 21 to Bay 24 of
Wan Shing Street were handover to HEC;
Slab at +3.10mPD and
+3.77 mPD and wall below were completed for the WSD Salt Water Pumping Station;
Excavation and
lateral support for DSD receiving pits were completed;
D610 pipe pile wall
construction at landside cofferdam of salt water intake culvert;
12 out of 12 nos of
pre-bored H-pile for box culverts N1 was casted as of 21November 2011;
Temporary working
platform was completed and pile cap construction was in progress at Portion 1B for the New Ferry Pier |
300mm thick topping
slab at northern portion was substantially completed on 20 January 2012.
Concreting of
structural slab at existing movable ramp was completed on 18 January 2012.
ABWFs and E&M
works of
Installation of glass
wall bearing at G/F and 1/F commenced on 22 December 2012 and completed on 5
January 2012.
ELS of Noise Barrier
NB2 was completed on 15 January 2012.
Blinding of Noise
Barrier NB2 footing was completed on 29 December 2012.
Steel fixing of
Noise Barrier NB2 was in progress.
Pedestrian diversion
above seawall coping Bay 4 to Bay 8 was implemented on 6 January 2011.
Bladder Tank steel
fixing and formwork erection are in progress.
E&M of P7, P8
& P9 were in progress.
Sheet piling works
of the Jacking pit at ex-pet garden commenced on 19 December 2011for the
heading construction of cooling mains across
Approximate 30m
cooling water pipe was laid at Harbour Centre,
Approximate 10m
cable duct was laid at
Trench excavation
and cooling mains installation along
Installation of PVC
and G.I cable ducts was ongoing at
+5.17 mPD and wall
below were completed on 12 Jan 2012 for the WSD Salt Water Pumping Station.
D610 pipe pile wall
construction at landside cofferdam of salt water intake culvert was in
progress.
Setting-up of pile
load test at WSD Seaside Cofferdam was completed on 17 January 2012.
Formwork removal for
remaining pile caps at Portion 1B for the New Ferry Pier was commenced on 20
January 2012.
Tower Crane
operation commenced on 16 January 2012 for the Ferry Pier construction.
Steel Mould
installation at Portion 1A and Welding
Steel for supporting Portion 2C of the New Ferry Pier was in progress.
Backfilling on the HDPE pipelines of Portion 2 between CH0 to CH150 was in
progress.
Steel deck support
for cooling main was completed on 30 December 2011 and cooling mains installation
was ongoing across WCR1.
Construction of
Temporary Decking Platform A for Vehicle Access of the New Wan Chai Ferry
Pier was completed on 30 December 2011.
Quad shore &
steel beam support installation commenced on 19 Jan 2012 in Box Culvert O;
Preparation works
for WCR2 diversion |
300mm thick topping
slab at southern portion andhelipad slab construction
Lighting
installation at Helipad
Removal of temporary
frame at existing movable ramp
Plate Support of
Safety Net at northern portion
ABWFs and E&M
works of Passenger Terminal Building (PTB)
Installation of
glass cladding at G/F and 1/F at PTB.
Roof waterproofing
test at PTB.
Concreting wall and
top slab of Bladder Tank
Concreting of Noise
Barrier NB2 upstand
Drilling holes for
anchor reinforcement fixing at Noise Barrier NB1
Erecting formwork of
Noise Barrier NB1
Mass concrete at
seawall coping Bay1 and Bay2.
Breaking up the
cover walkway footing of EVA at
E&M of P7, P8
& P9
+1.35mPD steel
platform of P7 was completed on 20 February 2012, P8 & P9 installation
Wet Well penstock
installation at P7, P8 & P9.
23 steel pipes of
WSD pipe jacking drive in TBM
Annulus chemical
grout surrounding the steel sleeve
Excavation and
lateral support of the Jacking pit at ex-pet garden for the cooling mains
construction across HHR.
Approximate 60m
cooling water pipe was laid at Harbour Centre,
Approximate 15m
cable duct was laid at
Casting of 800mm
thick slab @ +8.36mPD for the WSD Salt Water Pumping Station.
Excavation of 610
pipe pile wall landside cofferdam of salt water intake culvert
Pile load test at
WSD Seaside Cofferdam
Fabrication of
temporary water tank at Portion 1A was in progress. Installation of temporary
water tank for construction of pile caps & beams at Portion 1A
Formwork and
temporary working platform removal for pile caps at Portion 1B at New Wan
Chai Ferry Pier
Welding of steel
supports at Portion 2C of the New Ferry Pier
Backfilling on the
HDPE pipelines and diffuser section between CH0 & CH150
Cooling mains
installation across WCR1
Quad shore &
steel beam support installation at Box Culvert O
Installation of
Temporary Decking Platform "C" |
Table IV   Principle Work
Activities for Contract no. HY/2009/15
December 2011 |
January 2012 |
February 2012 |
Seawall block
construction and reclamation work at TS4;
Night time
protection works at CHT; and
Precautionary works
at Abutment A |
Seawall block
construction and reclamation work at TS4;
Night time
protection works at CHT; and
Precautionary works
at Abutment A |
Reclamation works at
TS4/ME4
Diaphragm wall
construction preparation works at TS4
Marine SI at TS2
ELS works at TS1 and
TPCWAE
Night time
protection works at CHT Cut off wall preparation works at |
Table V    Principle Work
Activities for Contract no. HK/2010/06
December 2011 |
January 2012 |
February 2012 |
Installation of
bored pile casing;
Excavation of bored
piles; and
Concreting of bored
piles |
Installation of
bored pile casing
Excavation of bored
piles
Concreting of bored
piles
Coring works |
Construction of
Pre-cast Unit in
Excavation of bored
piles
Concreting of bored
piles
Coring works |
Table VI   Principle Work
Activities for Contract no. HY/2009/19
December 2011 |
January 2012 |
February 2012 |
N/A |
N/A |
Marine bored piling |
Noise Monitoring
Three limit level exceedances at M1a on 29 November, 6 December 2011and 10 January 2012
during restricted hour.
No Action Level exceedance was recorded.
Real-time Noise Monitoring
Air Quality Monitoring
CMA1b: from 4 January 2012 to 5 January
2012
       from 10 January 2012 to 11
January 2012
       from 20 January 2012 to 21
January 2012
       from 26 January 2012 to 27
January 2012
from 13 February 2012 to 16
February 2012
CMA3a: from 16 January 2012 to 17
January 2012
 /span>from 13 February 2012 to 14 February 2012
CMA5a: from 18 February 2012 to
20 February 2012
Water Quality Monitoring
Complaints, Notifications of
Summons and Successful Prosecutions
1.1.1.
Lam
Geotechnics Limited (LGL) has been appointed to work as the Environmental Team
(ET) under Environmental Permit no. EP-356/2009 and Further Environmental
permit nos. FEP-01/356/2009, FEP-02/356/2009, FEP-03/356/2009, FEP-04/356/2009 and FEP-05/356/2009 to implement the Environmental Monitoring and
Audit (EM&A) programme as stipulated in the EM&A Manual of the approved
Environmental Impact Assessment (EIA) Report for Wan Chai Development phase II
and Central-Wan Chai Bypass (Register No.: AEIAR-125/2008) and in the EM&A
Manual of the approved EIA Report for Central-Wan Chai Bypass and Island
Eastern Corridor Link (Register No. AEIAR-014/2001).
1.1.2.
This
report presents the environmental monitoring and auditing work carried out in
accordance to the Section 10.4 of EM&A Manual and  /span>Environmental
Monitoring and Audit Requirements /span> under Particular
Specification Section 27.
1.1.3.
This report documents the finding of EM&A works
during the period from 28th November 2011 to 27th February
2012.
Section 1     Introduction  details the scope and structure of the
report.
Section 2     Project Background  summarizes
background and scope of the project, site description, project organization and
contact details of key personnel during the reporting period.
Section 3     Monitoring Requirements  summarizes all monitoring parameters,
monitoring locations, monitoring frequency, duration and action plan.
Section 4     Monitoring Results  summarizes the
monitoring results obtained in the reporting period.
Section 5     Compliance Audit  summarizes the auditing of
monitoring results, all exceedances environmental parameters.
Section 6     Complaints, Notification of summons and
Prosecution  summarizes the cumulative statistics on complaints,
notification of summons and prosecution
Section 7     Cumulative Construction Impact due to the
Concurrent Projects  summarizes the relevant cumulative
construction impact due to the concurrent activities of the concurrent Projects.
Section 8     Conclusion
2.1.1.
“Wan
Chai Development phase II and Central-Wan Chai Bypass and “Central-Wan Chai
Bypass and Island Eastern Corridor Link (hereafter called “the Project  are
Designed Project (DP) under the Environmental Impact Assessment Ordinance (Cap.
499) (EIAO). The Environmental Impact
Assessment (EIA) Reports for Central-Wan Chai Bypass and
2.1.2.
The
key purpose of Wan Chai Development Phase II (WDII) is to provide land at Wan
Chai North and North Point for construction of the Central-Wan Chai Bypass and
Island Eastern Corridor Link (CWB). Land formed under the project will be
developed as a world-class waterfront promenade joining that at the new Central
waterfront for public enjoyment.
2.1.3.
There
is a compelling and present need for the CWB to provide relief to the very
congested
2.2.1.
The
Project is located mainly in Wan Chai North,
2.2.2.
The
study area encompasses existing developments along the Wan Chai,
2.2.3.
The scope of the Project comprises:
 -
Land formation for key transport infrastructure and
facilities, including the Trunk Road (i.e. CWB) and the associated slip roads for
connection to the Trunk Road and for through traffic from Central to Wan Chai and
Causeway Bay. The land formed for the above transport infrastructure will provide
opportunities for the development of an attractive waterfront promenade for the
enjoyment of the public
 -
Reprovisioning / protection of the existing
facilities and structures affected by the land formation works mentioned above
 -
Extension, modification, reprovisioning or
protection of existing storm water drainage outfalls, sewerage outfalls and
watermains affected by the revised land use and land formation works mentioned
above
 -
Upgrading of hinterland storm water drainage system
and sewerage system, which would be rendered insufficient by the land formation
works mentioned above
 -
Provision of the ground level roads, flyovers,
footbridges, necessary transport facilities and the associated utility services
 -
Construction of the new waterfront promenade,
landscape works and the associated utility services
 -
The Trunk Road (i.e. CWB) within the study area and
the associated slip roads for connection to the Trunk Road.
2.2.4.
The
project also contains various Schedule 2 DPs that, under the EIAO, require
Environmental Permits (EPs) to be granted by the DEP before they may be either
constructed or operated. Table 2.1 summarises the five
individual DPs under this Project.
Figure 2.1 shows the locations of these Schedule 2 DPs.
Table
2.1   Schedule 2 Designated Projects
under this Project
Item |
Designated Project |
EIAO Reference |
Reason for inclusion |
DP1 |
Central-Wanchai Bypass (CWB) including its road tunnel and slip roads |
Schedule 2, Part I, A.1 and A.7 |
Trunk road and road tunnel more than 800 m in length |
DP2 |
Road P2 and other roads which are classified as primary/district
distributor roads |
Schedule 2, Part I, A.1 |
Primary / district distributor roads |
DP3 |
Reclamation works including associated dredging works |
Schedule 2, Part I, C.1 and C.12 |
Reclamation more than 5 ha in size and a dredging operation less than
100 m from a seawater intake point |
DP5 |
Wan Chai East Sewage Outfall |
Schedule 2, Part I, F.5 and F.6 |
Submarine sewage pipelines with a total diameter more than 1,200 mm
and include a submarine sewage outfall |
DP6 |
Dredging for the Cross-harbour Water Mains from Wan Chai to Tsim Sha
Tsui |
Schedule 2, Part I, C.12 |
A dredging operation less than 100 m from a seawater intake point |
2.3.1.
Due
to the multi-contract nature of the Project, there are a number of contracts
sub-dividing the whole works area into different work areas to be
commenced. Contractors of individual
contracts will be required by the EP holder to apply Further Environmental
Permits (FEP) such that the impact monitoring stations are sub-divided
accordingly to facilitate the implementation of EM&A programme and to
streamline the EM&A reporting for individual FEP holders correspondingly.
2.3.2.
The
details of individual contracts are summarized in Table2.2.
Table
2.2  Details of Individual Contracts
under the Project
Contract
No. |
Contract Title |
Associated
DP(s) |
Construction
Commencement Date |
HK/2009/01 |
Wan Chai Development Phase II  Central –Wanchai Bypass at |
DP3, DP6 |
23 July 2010 |
DP1, DP2 |
25 August 2011 |
||
HK/2009/02 |
Wan Chai Development Phase II  Central  Wan Chai Bypass at WanChai
East |
DP3, DP5 |
5 July 2010 |
DP1 |
26 April 2011 |
||
HY/2009/11 |
Wan Chai Development Phase II and Central  Wan Chai Bypass  North
Point Reclamation |
DP3 |
17 March 2010 (Under applicationof surrender) |
HY/2009/15 |
Central-Wanchai Bypass  Tunnel ( |
DP3 |
10 November 2010 |
DP1 |
13 July 2011 |
||
HK/2010/06 |
Wan Chai Development Phase II-Central-Wan Chai Bypass over MTR Tsuen
Wan Line |
DP3 |
22 March 2011 |
04/HY/2006 |
Reconstruction of Bus Terminus near |
DP1 |
September 2010 |
HY/2009/17 |
Central - Wan Chai Bypass (CWB) at FEHD Whitfield Depot - Advanced
piling works. |
DP1 |
5 October 2010 |
HY/2009/18 |
Central - Wan Chai Bypass (CWB)  Central Interchange |
DP1 |
21 April 2011 |
HY/2009/19 |
Central - Wanchai Bypass Tunnel (North Point Section) and Island
Eastern Corridor Link |
DP1 |
24 March 2011 |
2.4.1.
Civil Engineering and Development Department and
Highways Department are the overall project controllers for the Wan Chai
Development Phase II and Central-Wan Chai Bypass respectively. For
the construction phase of the Project, Project Engineer, Contractor(s),
Environmental Team and Independent Environmental Checker are appointed to
manage and control environmental issues.
2.4.2.
The
proposed project organization and lines of communication with respect to
environmental protection works are shown in
Figure 2.2. Key
personnel and contact particulars are summarized in Table 2.3:
Table 2.3  Contact Details of Key Personnel
Party |
Role |
Post |
Name |
Contact No. |
Contact Fax |
AECOM |
Engineer for WDII |
Principal Resident Engineer |
Mr. Frankie Fan |
2587 1778 |
2587 1877 |
Engineer for CWB |
Principal Resident Engineer |
Mr. Peter Poon |
3916 1818 |
3529 2829 |
|
|
Contractor under Contract no. HY/2009/11 |
Project Director |
Mr. Cho Yu Fun |
3157 1086 |
3157 1085 |
Project
Manager |
Mr. Gregory Wong |
3157 1086 |
|||
Site Agent |
Mr. Daniel Cheung |
3157 1086 |
|||
Environmental
Officer |
Mr. C. M. Wong |
3157 1086 |
|||
Chun Wo  Leader Joint Venture |
Contractor under Contract no. HK/2009/01 |
Project Director |
|
9124 2471 |
2634 1626 |
Site Agent |
Mr. Paul Yu |
9456 9819 |
|||
Operation
Manager |
Mr. Lau Yee Ching |
9466 3918 |
|||
Construction
Manager |
Mr. Wyman
Wong |
9627 2467 |
|||
Construction
Manager |
Mr. Jack Chu |
9775 3008 |
|||
Construction
Manager |
Mr. KK Yuen Mr. Andy Yu |
9498 1213 96484896 |
|||
Environmental
Officer (Compliance Manager) |
Mr. Andy Mak
|
9103 2370 |
|||
Chun Wo  CRGL Joint Venture |
Contractor under Contract no. HK/2009/02 |
Project Manager |
Mr. Chan Sing Cho |
3658 3002 |
2827 9996 |
Site Agent |
Mr. Mak Kam Wing |
3658 3044 |
|||
Quality & Environmental Manager |
Mr. C.P. Ho |
3658 3000 |
|||
Environmental Officer |
Ms. |
3658 3064 |
|||
|
Contractor under Contract no. HY/2009/15 |
Project Manager |
Mr. M Y Wong |
2823 7879 |
2528 5651 |
Site Manager |
Mr. P J Fan |
3557 6368 |
2566 2192 |
||
|
|
Construction Manager |
Mr. C K Kwok |
3557 6393 |
2566 2192 |
|
|
Construction Manager (East) |
Gene Cheung |
3557 6395 |
2566 2192 |
|
|
Construction Manager (West) |
Tony Chiu |
9090 0606 |
|
|
|
Environmental Officer |
Mr. Daniel Sin |
3557 6215 |
|
Gammon -Leader JV |
Contractor under Contract no. HK/2010/06 |
Project
Manager |
Mr. Paul Lui |
9095 7922 |
2529 2880 |
Site Agent |
Mr. Keith Tse |
2529 2068 |
|||
Environmental
Officer |
Mr. Lee Wai Man |
9481 6024 |
|||
Chun Wo - CRGL - MBEC Joint Venture |
Contractor under Contract no. HY/2009/19 |
Project Manager |
Mr. Rayland Lee |
3758 8879 |
2570 8013 |
Site Agent |
Mr. Cheung Kit Cheung |
6909 1555 |
|||
Environmental
Engineer |
Mr. Simon Wong |
9281 4346 |
|||
Environmental Manager / Environmental
Officer |
Mr. M.H. Isa |
9884 0810 |
|||
Construction Manager (Marine) |
William Luk |
9610 1101 |
|||
Construction Manager (Land) |
Patrick Cheung |
9643 3012 |
|||
ENVIRON Hong Kong Limited |
Independent
Environmental Checker (IEC) |
Independent Environmental Checker (IEC) |
Mr. David Yeung |
3743 0788 |
3548 6988 |
Lam Geotechnics Limited |
Environmental
Team (ET) |
Environmental Team Leader (ETL) |
Mr. Raymond Dai |
2882 3939 |
2882 3331 |
2.5.1.
During
this reporting period, the principle work activities for Contract no.
HY/2009/11 are summarized in Table2.4.
Table
2.4   Principle Work Activities for Contract
no. HY/2009/11
December 2011 |
January 2012 |
February 2012 |
Reclamation works;
Geo-textile laying;
Slotted panel
fixing;
Drainage
Construction works;
Installation of berm
blocks;
Concreting the
slopes of Open Channel U;
Construction of
in-situ mass concrete cooping;
Construction of
granite facing stone; and
Construction of
Seawall Type 8 |
The major work
activities for Contract no. HY/2009/11 was confirmed substantial complete by
RSS on 4 January 2012. The construction site was handed over to contractor
HY/2009/19 and the FEP-01/356/2009 was under application of surrender in this
reporting period. |
The major work
activities for Contract no. HY/2009/11 was confirmed substantial complete by
RSS on 4 January 2012. The construction site was handed over to contractor
HY/2009/19 and the FEP-01/356/2009 was under application of surrender in this
reporting period. |
2.5.2.
During
this reporting period, the principle work activities for Contract no.
HK/2009/01 are summarized in Table 2.5.
Table 2.5   Principle Work
Activities for Contract no. HK/2009/01
December 2011 |
January 2012 |
February 2012 |
Dredging works
within HKCEC Water Channel from CH190 to CH260 for Type 1 & 2
Sediment was commences and substantially completed;
Removal of rock
armours from CH150 to CH180 at the North bank of HKCEC Water
Channel was
commenced and substantially completed;
A trial for Type 3
sediment disposal was carried out;
Installation of
sheet pile for cooling water intake at Dome Promenade between
CH120 and CH170;
Installation of
precast RC outfall at Zone B1-3;
Trench excavation
for the 4 nos. of cooling water discharge pipes at B1-3;
Reclamation of
HKCEC3W (up to CH130) within HKCEC Water Channel;
Installation of
cross -harbour water mains nos. B13, A14/B14 and A15/ B15;
Thrust block
construction for A9/B9 and A11/B11 was commenced;
Concrete coating at
flange joint of cross-harbour water mains nos. A7B7/A8B8,
A8B8/A9B9 and
A9B9/A10B10;
Rockfilling and rock
protection to cross-harbour watermains;
Installation of pipe
pile at TST (Land Portion) was commenced and substantially completed;
Grouting works at
TST seafront along the pipe piles
Dredging of Type 2
sediment from CH50 to CH250 for subsequent cross-harbour
watermains
installation off Tsim Sha Tsui;
Mainlaying works at
Zone B1-5B, B1-6, B2-2, B4-2, B4-5, A1-5A, A3-2A, HKCEC,Zone B1-6, B2-2 and B1-5B; Zone A1-5A1 and A3-5B;
Way In/Out, A2-3B
and A5-5;
Coring and Grouting
works for external wall of cooling pumping stations Nos. P4 & P5 at Zone B4-5;
Coring works for
external wall of cooling pumping station No P1 at Zone B4-2;
Heading No. H3,H4, H5, H7 and H13; was substantially completed.
GI duct laying works
at ZoneA4-3A and Zone A4-3B;
Trench excavation,
pipe laying works and chamber construction for a 1000 dia.
watermains (CHF) at |
Dredging works
within HKCEC Water Channel from CH190 to CH260 for Type 3 sediment was
commended.
Removal of rock
armours from CH160 to CH260 at the north bank of HKCEC Water Channel was
substantially completed.
Installation of
sheet pile for cooling water intake at Dome Promenade between CH120 and CH170
was in progress.
Reclamation of
HKCEC3W (up to CH130) within HKCEC Water Channel has been substantially
completed.
Installation of 4
nos. of submersible cooling water discharge pipes at B1-3 was substantially
completed.
Thrust block
construction for A9B9, A11B11, A12B12 and A13B13 were completed.
Concrete coating at
flange at joint of cross-harbour watermains nos. A10B10/A11B11, A11B11/A12B12
and A12B12/A12B13 were completed.
Rockfilling and rock
protection to cross-harbour watermains was currently in progress.
Grouting works at
TST seafront along the pipe pile wall was commenced.
Installation of pipe
pile at TST (Sea Protection) was substantially completed.
Dredging of Type 3
sediment at designated disposal site was carried out.
Mainlaying works at
Zone B1-5B, B1-6, B2-2, A3-2A, A3-5B and were in progress.
Cable ducting works
at Zone B5-2 was commenced.
Mainlaying works and
subsequent reinstatement in Zone B4-5 was completed.
Mainlaying works and
subsequent carriageway reinstatement in Zone A1-5A1, A4-3A,
A4-3B and HKCEC Way
In/Out had been completed.
Mainlaying works and
subsequent carriageway reinstatement in Zone A2-3B and A2-4A was completed.
Coring and grouting
works for external wall of cooling pumping station No. P1 at Zone B4-2 was
completed.
Pipe laying works at
Zone B4-2 was completed and GI ducting works was in progress.
Jacking pit
establishment for pipe laying works by heading method at Zone A1-5A1 has been
completed.
Mainlaying and
chamber construction works at the traffic island neat junction of
Trench excavation,
pipe laying works and chamber construction for a 1000 dis. Warermains (CHF)
at
Trench excavation
and pipe laying works for a 1000 dia. Watermains (CHE) at |
Marine Works
Dredging works
within HKCEC water Channel form CH190 to Ch260 for Type 2 sediment and Type 3 sediment.
Installation of sheet
pile for cooling water intake at Dome Promenade between CH120 and CH170
Reclamation of
HKCEC3W (up to CH140) within HKCEC Water Channel
Seawall
reinstatement and retaining wall construction at Wan Chai Lanfill in Zone
B1-3 Cross-harbour Watermains Installation
Rockfilling and rock
protection to cross-harbour watermains
Grouting works at
TST seafront along the pipe pile wall
Installation of pipe
pile at TST seafront for pre-splitting seawall blocks
Trench excavation
and installation of shoring system along the pipe pile wall at TST seafront
Dredging of Type 3
sediment from CH50 to CH250 for subsequent cross-habour watermains installation
off TST
Dredging works
underneath Avenue of Stars carried by telescopic excavator
Dredging works in
confined water by 9 in 1 barge
1.1.3 Fresh
Watermains, Cooling Watermains and Salt Watermains (On Land)
Mainlaying works at
Zone B1-3, B1-5, B1-6, B2-2, B4-2, B4-4, B5-2, A1-1, A2-3C, A3-4B, A3-5B and
A4-2A, B4-4, A4-2A, A1-1,
A1-4A, A2-3C and A3-4B
Mainlaying works and
subsequent carriageway reinstatement in Zone A5-5 and A3-2A
Cable ducting works
along
Heading No. H5, H7, H8 and H13 (mainlaying
woks by trenchless method)
Mainlaying and
chamber construction works at the traffic island near junction of Trench excavation, pipe laying works and chamber construction
for a 1000 dia. watermains (CHF and CHE) at |
2.5.3.
During
this reporting period, the principle work activities for Contract no.
HK/2009/02 are summarized in Table 2.6.
Table
2.6   Principle Work Activities for
Contract no. HK/2009/02
December 2011 |
January 2012 |
February 2012 |
300mm thick topping
slab together with the make up slab below at northern portion commenced on 30 Nov
2011;
Concreting at Roof
Plinth, lift shaft up to +14.15mPD and Fire Service Pump room up to +14.15mPD of
Passenger Terminal Building were completed;
E&M and ABWF of
ELS of Noise Barrier
2 commenced on 29 Nov 2011 and nearly completed.
Casting of
pedestrian pavement above seawall coping Bay 4 to Bay 8 was completed on 13 December 2011;
Casting of the bus
shelter footing at
Precast slab
installation at the existing movable ramp was in progress;
Saw cutting of
existing slabs for the construction NB1 footing was completed;
E&M of P7, P8
& P9
Approximate 50m
cooling water pipe was laid at Harbour Centre,
Jacking pit at
ex-pet garden for the heading construction of cooling mains across
Convention Avenue
commenced;
Approximate 50m
cable duct was laid at
Construction of wash
out chamber at Centre were
completed;
Trench excavation
and cooling mains installation along
Installation of PVC
and G.I cable ducts was ongoing at
Installation of
submarine outfall pipe was completed;
Dredging for
submarine outfall pipe was ongoing;
Concreting the Base
Slab of Wan Shing Street at Bay 24 was completed;
Concreting the wall
shaft and roof slab completed of Bay 24 were
completed;
Bay 21 to Bay 24 of
Wan Shing Street were handover to HEC;
Slab at +3.10mPD and
+3.77 mPD and wall below were completed for the WSD Salt Water Pumping
Station;
Excavation and
lateral support for DSD receiving pits were completed;
D610 pipe pile wall
construction at landside cofferdam of salt water intake culvert;
12 out of 12 nos of
pre-bored H-pile for box culverts N1 was casted as of 21November 2011;
Temporary working
platform was completed and pile cap construction was in progress at Portion
1B for the New Ferry Pier |
300mm thick topping
slab at northern portion was substantially completed on 20 January 2012.
Concreting of
structural slab at existing movable ramp was completed on 18 January 2012.
ABWFs and E&M
works of
Installation of glass
wall bearing at G/F and 1/F commenced on 22 December 2012 and completed on 5
January 2012.
ELS of Noise Barrier
NB2 was completed on 15 January 2012.
Blinding of Noise
Barrier NB2 footing was completed on 29 December 2012.
Steel fixing of
Noise Barrier NB2 was in progress.
Pedestrian diversion
above seawall coping Bay 4 to Bay 8 was implemented on 6 January 2011.
Bladder Tank steel
fixing and formwork erection are in progress.
E&M of P7, P8
& P9 were in progress.
Sheet piling works
of the Jacking pit at ex-pet garden commenced on 19 December 2011for the
heading construction of cooling mains across
Approximate 30m
cooling water pipe was laid at Harbour Centre,
Approximate 10m
cable duct was laid at
Trench excavation
and cooling mains installation along
Installation of PVC
and G.I cable ducts was ongoing at
+5.17 mPD and wall
below were completed on 12 Jan 2012 for the WSD Salt Water Pumping Station.
D610 pipe pile wall
construction at landside cofferdam of salt water intake culvert was in
progress.
Setting-up of pile
load test at WSD Seaside Cofferdam was completed on 17 January 2012.
Formwork removal for
remaining pile caps at Portion 1B for the New Ferry Pier was commenced on 20
January 2012.
Tower Crane
operation commenced on 16 January 2012 for the Ferry Pier construction.
Steel Mould
installation at Portion 1A and Welding
Steel for supporting Portion 2C of the New Ferry Pier was in progress.
Backfilling on the HDPE pipelines of Portion 2 between CH0 to CH150 was in
progress.
Steel deck support
for cooling main was completed on 30 December 2011 and cooling mains
installation was ongoing across WCR1.
Construction of
Temporary Decking Platform A for Vehicle Access of the New Wan Chai Ferry
Pier was completed on 30 December 2011.
Quad shore &
steel beam support installation commenced on 19 Jan 2012 in Box Culvert O;
Preparation works
for WCR2 diversion |
300mm thick topping
slab at southern portion andhelipad slab construction
Lighting
installation at Helipad
Removal of temporary
frame at existing movable ramp
Plate Support of
Safety Net at northern portion
ABWFs and E&M
works of Passenger Terminal Building (PTB)
Installation of
glass cladding at G/F and 1/F at PTB.
Roof waterproofing
test at PTB.
Concreting wall and
top slab of Bladder Tank
Concreting of Noise
Barrier NB2 upstand
Drilling holes for
anchor reinforcement fixing at Noise Barrier NB1
Erecting formwork of
Noise Barrier NB1
Mass concrete at
seawall coping Bay1 and Bay2.
Breaking up the
cover walkway footing of EVA at
E&M of P7, P8
& P9
+1.35mPD steel
platform of P7 was completed on 20 February 2012, P8 & P9 installation
Wet Well penstock
installation at P7, P8 & P9.
23 steel pipes of
WSD pipe jacking drive in TBM
Annulus chemical
grout surrounding the steel sleeve
Excavation and
lateral support of the Jacking pit at ex-pet garden for the cooling mains
construction across HHR.
Approximate 60m
cooling water pipe was laid at Harbour Centre,
Approximate 15m
cable duct was laid at
Casting of 800mm
thick slab @ +8.36mPD for the WSD Salt Water Pumping Station.
Excavation of 610
pipe pile wall landside cofferdam of salt water intake culvert
Pile load test at
WSD Seaside Cofferdam
Fabrication of
temporary water tank at Portion 1A was in progress. Installation of temporary
water tank for construction of pile caps & beams at Portion 1A
Formwork and
temporary working platform removal for pile caps at Portion 1B at New Wan
Chai Ferry Pier
Welding of steel
supports at Portion 2C of the New Ferry Pier
Backfilling on the
HDPE pipelines and diffuser section between CH0 & CH150
Cooling mains
installation across WCR1
Quad shore &
steel beam support installation at Box Culvert O
Installation of
Temporary Decking Platform "C" |
2.5.4.
Major construction activities for Contract no.
HY/2009/15 was commenced on 10 November 2010. During this reporting period, the
principle work activities for Contract no. HY/2009/15 are summarized as below:
Table
2.7   Principle Work Activities for Contract no. HY/2009/15
December 2011 |
January 2012 |
February 2012 |
Seawall block
construction and reclamation work at TS4;
Night time
protection works at CHT; and
Precautionary works
at Abutment A |
Seawall block
construction and reclamation work at TS4;
Night time
protection works at CHT; and
Precautionary works
at Abutment A |
Reclamation works at
TS4/ME4
Diaphragm wall
construction preparation works at TS4
Marine SI at TS2
ELS works at TS1 and
TPCWAE
Night time
protection works at CHT Cut off wall preparation works at |
2.5.5.
Contract
no. HK/2010/06 was commenced on 22 March 2011. During this reporting period,
the principle work activities for Contract no. HK/2010/06 are summarized as
below:
Table
2.8   Principle Work Activities for Contract no. HK/2010/06
December 2011 |
January 2012 |
February 2012 |
Installation of
bored pile casing;
Excavation of bored
piles; and
Concreting of bored
piles |
Installation of
bored pile casing
Excavation of bored
piles
Concreting of bored
piles
Coring works |
Construction of
Pre-cast Unit in
Excavation of bored
piles
Concreting of bored
piles
Coring works |
Table 2.9  Principle Work Activities
for Contract no. HY/2009/19
December 2011 |
January 2012 |
February 2012 |
N/A |
N/A |
Marine bored piling |
2.5.7.
Implementation
status of the recommended mitigation measures during this reporting period is
presented in
Appendix 2.1.
Noise Monitoring Stations
3.1.1.
The
noise monitoring stations for the Project are listed and shown in Table
3.1 and
Figure 3.1. Appendix 3.1 shows
the established Action/Limit Levels for the monitoring works.
Table 3.1  Noise Monitoring Stations
Station |
Description |
M1a |
Harbour Road Sports Centre |
M2b |
Noon Gun Area |
M3a |
Tung Lo Wan Fire
Station |
M4b |
Victoria Centre |
M5b |
|
M6 |
HK |
Real
time Noise Monitoring Stations
3.1.1.
The real-noise monitoring stations for the Project are
listed and shown in Table 3.2 and
Figure 3.1..
Appendix 3.1 shows the established Action/Limit Levels for the
monitoring works.
Table 3.2  Real Time Noise Monitoring Station
District |
Station |
Description |
Tin Hau |
RTN1 |
FEHD Hong Kong Transport Section Whitefield Depot |
North Point |
RTN2 |
Oil Street Community Liaison Centre |
Noise Monitoring
Parameters, Frequency and Duration
3.1.2.
The construction
noise level shall be measured in terms of the A-weighted equivalent continuous sound
pressure level (Leq). Leq (30 minutes) shall be used as
the monitoring parameter for the time period between 0700
and 1900 hours on normal weekdays. For all other time periods, Leq (5
minutes) shall be employed for comparison with the Noise Control
Ordinance (NCO) criteria.
Supplementary information for data auditing, statistical results such as L10
and L90 shall also be obtained for reference.
3.1.3.
Noise monitoring
shall be carried out at all the designated monitoring stations. The monitoring
frequency shall depend on the scale of the construction activities. The
following is an initial guide
on the regular monitoring frequency for each station on a weekly basis when
noise generating activities are underway:
 -
one
set of measurements between 0700 and 1900 hours on normal weekdays.
3.1.4.
If construction works are extended to
include works during the hours of 1900  0700 as well as public holidays and
Sundays, additional weekly impact monitoring shall be carried out during
respective restricted hours periods. Applicable permits under NCO shall be
obtained by the Contractor.
3.1.5.
Real
time noise shall be carried out at the designated monitoring stations. The
following is an initial guide on the regular monitoring frequency for each
station on a 24 hours daily basis when noise generating activities are
underway:
 -
One
set of measurements between 0700 and 1900 hours on normal weekdays.
 -
One
set of measurements between 1900 and 2300 hours on normal weekdays and 0700 and
2300 hours on public holidays.
 -
One
set of measurements between 2300 and 0700 hours on next day on everyday.
3.1.6.
Noise
baseline level review was commenced in this reporting period. Detailed review
report showed in
Appendix 3.2.
3.1.7.
Real
time noise baseline level review at night time period (2300 to 0700) was
commenced in this reporting period. Detailed review report showed in
Appendix 3.3.
Monitoring Equipment
3.1.8.
As referred to in the Technical Memorandum  issued
under the NCO, sound level meters in compliance with the International
Electrotechnical Commission Publications 651: 1979 (Type 1) and 804: 1985 (Type
1) specifications shall be used for carrying out the noise monitoring.
Immediately prior to and following each noise measurement the accuracy of the
sound level meter shall be checked using an acoustic calibrator generating a
known sound pressure level at a known frequency. Measurements may be accepted
as valid only if the calibration level from before and after the noise
measurement agree to within 1.0 dB.
3.1.9.
Noise measurements shall not be made in fog, rain,
wind with a steady speed exceeding 5 m/s or wind with gusts exceeding 10 m/s.
The wind speed shall be checked with a portable wind speed meter capable of
measuring the wind speed in m/s.
Air Quality Monitoring
Stations
3.2.1.
The
air monitoring stations for the Project are listed and shown in Table
3.3 and
Figure 3.1.
Appendix 3.1 shows the established
Action/Limit Levels for the monitoring works.
Table 3.3  Air Monitoring Stations
Station ID |
Monitoring
Location |
Description |
CMA1b |
Oil Street Community
Liaison Centre |
North Point |
CMA2a |
|
|
CMA3a |
CWB PRE Site Office * |
|
CMA4a |
Society for the
Prevention of Cruelty to Animals |
Wan Chai |
CMA5a |
Children Playgrounds
opposite to |
Wan Chai |
CMA6a |
WDII PRE Site Office * |
Wan Chai |
* Remarks: As per the ENPC meeting in January 2011,
the monitoring stations CMA3a - Future CWB site office at Wanchai Waterfront
Promenade and CMA6a - Future AECOM site office at Work Area were renamed as
remark.
Air Monitoring Parameters,
Frequency and Duration
3.2.2.
One-hour
and 24-hour TSP levels should be measured to indicate the impacts of
construction dust on air quality. The 24-hour TSP levels shall be measured by
following the standard high volume sampling method as set out in the Title 40
of the Code of Federal Regulations, Chapter 1 (Part 50), Appendix B.
3.2.3.
All
relevant data including temperature, pressure, weather conditions, elapsed-time
meter reading for the start and stop of the sampler, identification and weight
of the filter paper, and any other local atmospheric factors affecting or
affected by site conditions, etc., shall be recorded down in detail.
3.2.4.
For
regular impact monitoring, the sampling frequency of at least once in every
six-days, shall be strictly observed at all the monitoring stations for 24-hour
TSP monitoring. For 1-hour TSP monitoring, the sampling frequency of at least
three times in every six-days should be undertaken when the highest dust impact
occurs.
Sampling Procedure and
Monitoring Equipment
3.2.5
High volume samplers (HVSs) in compliance with the
following specifications shall be used for carrying out the 1-hour and 24-hour
TSP monitoring:
 -
0.6
- 1.7 m3 per minute adjustable flow range;
 -
equipped
with a timing / control device with +/- 5 minutes accuracy for 24 hours
operation;
 -
installed
with elapsed-time meter with +/- 2 minutes accuracy for 24 hours operation;
 -
capable
of providing a minimum exposed area of 406 cm2;
 -
flow
control accuracy: +/- 2.5% deviation over 24-hour sampling period;
 -
equipped
with a shelter to protect the filter and sampler;
 -
incorporated
with an electronic mass flow rate controller or other equivalent devices;
 -
equipped
with a flow recorder for continuous monitoring;
 -
provided
with a peaked roof inlet;
 -
incorporated
with a manometer;
 -
able
to hold and seal the filter paper to the sampler housing at horizontal
position;
 -
easily
changeable filter; and
 -
capable
of operating continuously for a 24-hour period.
3.2.6
Initial calibration of dust monitoring equipment
shall be conducted upon installation and thereafter at bi-monthly intervals.
The transfer standard shall be traceable to the internationally recognized
primary standard and be calibrated annually. The concern parties such as IEC
shall properly document the calibration data for future reference. All the data
should be converted into standard temperature and pressure condition.
Laboratory Measurement /
Analysis
3.2.7
A clean laboratory with constant temperature and
humidity control, and equipped with necessary measuring and conditioning
instruments to handle the dust samples collected, shall be available for sample
analysis, and equipment calibration and maintenance. The laboratory should be
HOKLAS accredited.
3.2.8
An alternative non-HOKLAS accredited laboratory was set-up for carrying out the laboratory analysis,
the laboratory equipment was
approved by the ER on 8 February 2011 and the
measurement procedures were
witnessed by the IEC. Any measurement performed by the laboratory was be demonstrated to the satisfaction of
the ER and IEC. IEC shall regularly audit to the measurement performed by the
laboratory to ensure the accuracy of measurement results.
3.2.9
Filter paper of size 8" x 10" shall be
labelled before sampling. It shall be a clean filter paper with no pinholes,
and shall be conditioned in a humidity-controlled chamber for over 24-hours and
be pre-weighed before use for the sampling.
3.2.10
After sampling, the filter paper loaded with dust
shall be kept in a clean and tightly sealed plastic bag. The filter paper shall
then be returned to the laboratory for reconditioning in the humidity
controlled chamber followed by accurate weighing by an electronic balance with
readout down to 0.1 mg. The balance shall be regularly calibrated against a
traceable standard.
3.2.11
All the collected samples shall be kept in a good
condition for 6 months before disposal.
impact monitoring for
odour patrol
3.2.12 Odour patrols
along the shorelines of Causeway Bay Typhoon Shelter and ex-Wan Chai Public
Cargo Working Area when there is temporary reclamation in Causeway Bay Typhoon
Shelter and/or in the ex-Wan Chai
Public Cargo Working Area, or when there is dredging of the odorous sediment
and slime at the south-western corner of the Causeway Bay Typhoon Shelter.
Odour patrols will be carried out at bi-weekly intervals during July, August and
September by a qualified person of the ET who shall:
 -
be
at least 16 years of age;
 -
be
free from any respiratory illnesses; and
 -
not
be allowed to smoke, eat, drink (except water) or use chewing gum or sweets 30
min
 -
before
and during odour patrol
3.2.13 Odour patrol shall be conducted by
independent trained personnel / competent persons patrolling and sniffing
around the shore as shown in
Figure 3.1 to detect any odour at the
concerned hours (afternoon is preferred for higher daily temperature).
3.2.14 The qualified person will use the nose
(olfactory sensor) to sniff odours at different locations. The main odour
emission sources and the areas to be affected by the odour nuisance will be identified.
3.2.15 The perceived odour intensity is to be
divided into 5 levels which are ranked in the descending order as follows:
 -
0 -
Not detected. No odour perceived or an odour so weak that it cannot be easily
characterized or described;
 -
1 -
Slight Identifiable odour, and slight chance to have odour nuisance;
 -
2 -
Moderate Identifiable odour, and moderate chance to have odour nuisance;
 -
3 -
Strong Identifiable, likely to have odour nuisance;
 -
4 -
Extreme Severe odour, and unacceptable odour level.
3.2.16 The findings including odour intensity,
odour nature and possible odour sources, and also the local wind speed and
direction at each location will be recorded. In addition, some relevant
meteorological and tidal data such as daily average temperature, and daily
average humidity, on that surveyed day will be obtained from the Hong Kong
Observatory Station for reference. The Action and Limit levels for odour patrol
are shown in
Appendix 3.1.
3.3.1.
The
EIA Report has identified that the key water quality impact would be associated
with the dredging works during the construction phase. Marine water quality monitoring for dissolved
oxygen (DO), suspended solid (SS) and turbidity is therefore recommended to be
carried out at selected WSD flushing water intakes. The impact monitoring should be carried out
during the proposed dredging works to ensure the compliance with the water
quality standards.
3.3.2.
The updated EM&A Manual for EP-356/2009 (Version
in March 2011) is approval by EPD on 29 April 2011. As such, the Action Level
and Limit Level for the wet season (April  September) will be effected and
applied to the water quality monitoring data from 30 April 2011.
Water Quality Monitoring Stations
3.3.3.
It
is proposed to monitor the water quality at 9 WSD salt water intakes and 14
cooling water intakes along the seafront of the
Table
3.4   Marine Water Quality
Stations for Water Quality Monitoring
Station Ref. |
Location |
Easting |
Northing |
WSD Salt Water Intake |
|||
WSD7 |
|
834150.0 |
818300.3 |
WSD9 |
Tai Wan |
837921.0 |
818330.0 |
WSD10 |
Cha Kwo Ling |
841900.9 |
817700.1 |
WSD15 |
Sai Wan Ho |
841110.4 |
816450.1 |
WSD17 |
|
839790.3 |
817032.2 |
WSD19 |
Sheung Wan |
833415.0 |
816771.0 |
WSD20 |
|
830750.6 |
816030.3 |
WSD21 |
Wan Chai |
836220.8 |
815940.1 |
RW1 |
Wan Chai (Reprovision) |
836188.8 |
815911.1 |
Cooling Water Intake |
|||
C1 |
HKCEC Extension |
835885.6 |
816223.0 |
C2 |
Telecom House |
835647.9 |
815864.4 |
C3 |
HKCEC Phase I |
835836.2 |
815910.0 |
C4e |
Wan |
835932.8 |
815888.2 |
C4w |
Wan |
835629.8 |
815889.2 |
C5e |
Sun Hung Kai Centre (Eastern) |
836250.1 |
815932.2 |
C5w |
Sun Hung Kai Centre (Western) |
836248.1 |
815933.2 |
C6 |
World Trade Centre |
837009.6 |
815999.3 |
C7 |
|
837193.7 |
816150.0 |
C8 |
|
837970.6 |
816957.3 |
C9 |
Provident Garden |
838355.0 |
817116.6 |
RC1 |
Proposed HKAPA Extension |
835487.7 |
815987.7 |
RC5 |
Sun Hung Kai Centre (Reprovision) |
836291.4 |
816029.7 |
RC7 |
|
837245.2 |
816156.6 |
Remarks: -   The cessation of
seawater intake operation for C6 was confirmed on 17 May 2011, the water
monitoring at C6 was then terminated since 17 May 2011.
        -  WSD9 and WSD17 were implemented with respect
to HK/2009/02 from 8 Feb 2012.
-  4-week water quality monitoring at WSD9,
WSD10, WSD15, WSD17, C8 and C9 were completed on 6 Feb 2012.
-  C8 and C9 were implemented with respect to
HY/2009/19 from 28 Jan 2012.
Water Quality Parameters
and frequency
3.3.4.
Monitoring
of dissolved oxygen (DO), turbidity and suspended solids (SS) shall be carried
out at WSD flushing water intakes and cooling water intakes. DO and Turbidity
are measured in-situ while SS is determined in laboratory. 
3.3.5.
In
association with the water quality parameters, other relevant data shall also
be measured, such as monitoring location/position, time, sampling depth, water
temperature, pH, salinity, dissolved oxygen (DO) saturation, weather
conditions, sea conditions, tidal stage, and any special phenomena and work
underway at the construction site etc.
3.3.6.
The
interval between two sets of monitoring should not be less than 36 hours except
where there are exceedances of Action and/or Limit Levels, in which case the
monitoring frequency will be increased. Table
3.5 shows the proposed monitoring frequency and water quality
parameters. Duplicate in-situ
measurements and water sampling should be carried out in each sampling
event. For selection of tides for
in-situ measurement and water sampling, tidal range of individual flood and ebb
tides should be not less than 0.5m.
Table 3.5  Marine Water Quality
Monitoring Frequency and Parameters
Activities |
Monitoring Frequency1 |
Parameters2 |
During the 4-week
baseline monitoring period |
Three days per week, at
mid-flood and mid-ebb tides |
Turbidity, Suspended
Solids (SS), Dissolved Oxygen (DO), pH, Temperature, Salinity |
During marine construction works |
Three days per week, at
mid-flood and mid-ebb tides |
Turbidity, Suspended
Solids (SS), Dissolved Oxygen (DO), pH, Temperature, Salinity |
After completion of marine construction works |
Three days per week, at
mid-flood and mid-ebb tides |
Turbidity, Suspended
Solids (SS), Dissolved Oxygen (DO), pH, Temperature, Salinity |
Notes:
1. For selection of tides for in-situ measurement and water sampling,
tidal range of individual flood and ebb tides should be not less than 0.5m.
2.
Turbidity should be
measured in situ whereas SS should be determined by laboratory.
Dissolved Oxygen and
Temperature Measuring Equipment
3.3.7.
The
instrument should be a portable, weatherproof dissolved oxygen measuring
instrument complete with cable, sensor, comprehensive operation manuals, and
use a DC power source. It should be capable of measuring:
 -
a
dissolved oxygen level in the range of 0-20 mg/l and 0-200% saturation
 -
a
temperature of 0-45 degree Celsius
3.3.8.
It
should have a membrane electrode with automatic temperature compensation
complete with a cable. Sufficient stocks of spare electrodes and cables should
be available for replacement where necessary. (e.g. YSI model 59 meter, YSI
5739 probe, YSI 5795A submersible stirrer with reel and cable or an approved
similar instrument).
3.3.9.
Should
salinity compensation not be build-in in the DO equipment, in-situ salinity
shall be measured to calibrate the DO equipment prior to each DO measurement.
Turbidity Measurement
Instrument
3.3.10
The instrument
should be a portable, weatherproof turbidity-measuring instrument complete with
comprehensive operation manual. The equipment should use a DC power source. It
should have a photoelectric sensor capable of measuring turbidity between 0‑1000
NTU and be complete with a cable (e.g. Hach model 2100P or an approved similar
instrument).
Sampler
3.3.11
 /span>Water
sampler comprises a transparent PVC cylinder, with a capacity of not less than
2 litres, and can be effectively sealed with latex cups at both ends. The
sampler should have a positive latching system to keep it open and prevent
premature closure until released by a messenger when the sampler is at the
selected water depth (e.g. Kahlsico Water Sampler or an approved similar
instrument).
Sample Container and
Storage
3.3.12
Water samples for suspended solids measurement
should be collected in high-density polythene bottles, packed in ice (cooled to
4°C without being frozen), and delivered to ALS Technichem (HK) Pty Ltd. as
soon as possible after collection for analysis.
Water Depth Detector
3.3.13
A portable, battery-operated echo sounder shall be
used for the determination of water depth at each designated monitoring
station. This unit can either be handheld or affixed to the bottom of the
workboat, if the same vessel is to be used throughout the monitoring programme.
Salinity
3.3.14
A portable salinometer capable of measuring
salinity in the range of 0-40 ppt shall be provided for measuring salinity of
the water at each of monitoring location.
Monitoring Position
Equipment
3.3.15
A hand-held or boat-fixed type digital Global
Positioning System (GPS) with waypoint bearing indication or other equivalent
instrument of similar accuracy shall be provided and used during monitoring to
ensure the monitoring vessel is at the correct location before taking
measurements.
Calibration of In-situ
Instruments
3.3.16
All in-situ monitoring instrument shall be checked,
calibrated and certified by a laboratory accredited under HOKLAS or equivalent
before use, and subsequently re-calibrated at 3 monthly intervals throughout
all stages of the water quality monitoring. Responses of sensors and electrodes
should be checked with certified standard solutions before each use. Wet bulb
calibration for a DO meter shall be carried out before measurement at each
monitoring location.
3.3.17
For the on site calibration of field equipment by
the ET, the BS 127:1993, "Guide to Field and on-site test methods for the
analysis of waters" should be observed.
3.3.18
Sufficient stocks of spare parts should be
maintained for replacements when necessary. Backup monitoring equipment shall
also be made available so that monitoring can proceed uninterrupted even when
some equipment is under maintenance, calibration, etc.
Laboratory Measurement /
Analysis
3.3.19
Analysis of suspended solids has been carried out
in a HOKLAS accredited laboratory, ALS Technichem (HK) Pty Ltd. Water samples
of about 1L shall be collected at the monitoring stations for carrying out the
laboratory SS determination. The SS determination work shall start within 24
hours after collection of the water samples. The SS determination shall follow
APHA 19ed or equivalent methods subject to the approval of IEC and EPD.
Enhanced Water
Quality Monitoring in the ex-Wan Chai Public Cargo
Working Area
and the
3.3.10. The enhanced water quality monitoring
and audit programme is to avoid aggravation of odour nuisance from seawater
arising from temporary reclamation in the ex-Wan Chai Public Cargo Working Area
and the Causeway Bay Typhoon Shelter.
3.3.11. Dissolved oxygen monitoring at the
intakes C6 and C7 in Causeway Bay Typhoon Shelter when there is temporary
reclamation in Causeway Bay Typhoon Shelter and at the south-western and
south-eastern corners of the ex-Wan Chai Public Cargo Working Area. The
proposed water quality monitoring stations of the Project are shown in Table
3.6 and
Figure 3.1.
Table 3.6   Marine
Water Quality Stations for Enhanced Water Quality Monitoring
Station |
Location |
C6 |
Excelsior Hotel |
C7 |
|
Ex-WPCWA-SW |
South-western of the ex-Wan Chai Public Cargo
Working Area |
Ex-WPCWA-SE |
South-eastern of the ex-Wan Chai Public Cargo
Working Area |
3.3.12. The monitoring of dissolved oxygen are
to be carried out 3 days per week, at mid-flood and mid-ebb tides for 3 water
depths (1m below water surface, mid-depth and 1m above sea bed, except where
the water depth less than 6m, the mid-depth may be omitted. If the water depth
be less than 3m, only the mid-depth will be monitored).
Daily SS
Monitoring and 24 hours Turbidity Monitoring System
3.3.13. During dredging of the sediment at the
south-western corner of the Causeway Bay Typhoon Shelter, daily monitoring of suspended solids and 24 hour
monitoring of turbidity at the cooling water intakes (C6 and C7) shall be conducted.
3.3.14. The 24 hours monitoring of turbidty at the
cooling water intakes (C6 and C7) shall be established
by setting up a continuous water quality monitoring station in front of the
intakes during the dredging activities. 
The monitoring system include the turbidity sensor and data logger which
is capable of data capturing at every 5 minutes.
The data shall
be downloaded daily and compared with the
Action and Limit level determined during the baseline water qualtiy monitoring
at the cooling water intake locations.
Additional Dissovled
oxygen Monitoring FOR CULVERT L WATER DISCHARGE FLOW
3.3.15
In
response to the Condition 2.18 of the Environmental Permit no. EP-356/2009
requiring that a silt curtain / impermeable barrier system be installed to
channel water discharge flow from Culvert L to locations outside the embayment
area, a proposed replacement of the requirement with additional dissolved
oxygen monitoring has been conducted at three monitoring stations, namely A, B
and C between the eastern seawall of Central Reclamation Phase III and the
HKCEC Extension since November 2011 under EP-356/2009 so that DO level between
the eastern seawall of Central Reclamation Phase II and the HKCEC extension
could be continuously monitored.
3.3.16
The
proposed DO monitoring stations of the Project are shown in Table 3.7
Table 3.7   Marine Water Quality Stations for Additional
DO Monitoring
Station |
Easting |
Northing |
A |
835468 |
815857 |
B |
835572 |
815961 |
C |
835659 |
816271 |
3.3.17
The
monitoring of dissolved oxygen are to be carried out once per week, at mid-flood
and mid-ebb tides for 3 water depths (1m below water surface, mid-depth and 1m
above sea bed, except where the water depth less than 6m, the mid-depth may be
omitted. If the water depth be equal to or less than 3m, only the mid-depth
will be monitored).
4.0.1.
The
environmental monitoring will be implemented based on the division of works
areas of each designed project managed under different contracts with separate
FEP applied by individual contractors. 
Overall layout showing work areas of various contracts, latest status of
work commencement and monitoring stations is shown in
Figure
2.1 and
Figure 3.1. The monitoring results are
presented in according to the Individual Contract(s).
4.0.2  The
major work activities for Contract no. HY/2009/11 was confirmed substantial
complete by RSS on 4 January 2012. The FEP surrender application
was submitted to EPD by contractor on 16 Jan 2012 that they would
surrender the permit on 1 Jan 2012. Moreover, the construction site was
handed over to contractor HY/2009/19 on 4 January 2012. However, the surrender
of the FEP for HY/2009/11 withdrew by contractor on 14 February 2012 due to
some outstanding works was confirmed by RSS on 10 Feb 2012.
Therefore, the noise, air and water quality monitoring were keeping in
view for the commencement of the works under this
contract. No construction activity was conducted by HY/2009/11 up to 4 January 2012.
4.0.3  /span>According to
EP-364/2009/A Part B, “Scale and Scope of Designated Project  Remarks (c),”The
permanent and temporary reclamation and associated dredging works related to
the CWB construction are separately covered by environmental permit No.
EP-356/2009 issued to Civil Engineering and Development Department  and
marine piling works to be conducted by the Contractor of Contract no. HY/2009/19
from 28 January 2012 was considered to be governed under EP-356/2009. As the
construction site area of Contract no. HY/2009/11 had already been handed over
to Contract no. HY/2009/19, the designated noise, water and air quality
monitoring stations for Contract no. HY/2009/11 would be shared with Contract
no. HY/2009/19 from 28 January 2012.
Contract no. HY/2009/11  Central  
Wanchai Bypass, North Point Reclamation
4.1.1.
The
proposed division of noise monitoring stations for Contract no. HY/2009/11 are
summarized in Table 4.1 below:
Table
4.1   Noise Monitoring Stations for Contract no.  /span>HY/2009/11
Station |
Description |
M4b |
Victoria Centre |
M5b |
|
4.1.2.
There
was no exceedance recorded in reporting period. Noise monitoring results
measured in this reporting period are reviewed and summarized. Details of graphical presentation can be
referred in
Appendix 4.1. 
Contract no. HK/2009/01 - Wan Chai
Development Phase II  Central –Wanchai Bypass at HKCEC and Contract no.
HK/2009/02 - Wan Chai Development Phase II  Central  Wan Chai Bypass at
WanChai East
4.1.3.
The
proposed division of noise monitoring stations are summarized in Table
4.2 below.
Table 4.2   Noise Monitoring Station for Contract nos. HK/2009/01 and HK/2009/02
Station |
Description |
M1a |
Harbour Road Sports Centre |
4.1.4.
Three limit level exceedances at M1a on 29
November, 6 December 2011 and 10 January 2012 during the restricted hour in reporting period.
Major noise source was contributed from
Contract no. HY/2009/15 - Central-Wanchai Bypass  Tunnel (
4.1.5.
The
noise monitoring for HY/2009/15 was commenced on 10 November 2010. The proposed division of noise
monitoring stations are summarized in Table 4.3 below.
Table
4.3   Noise Monitoring Station
for Contract nos. HY/2009/15
Station |
Description |
M2b |
Noon Gun Area |
M3a |
Tung Lo Wan Fire Station |
4.1.6.
There
was no exceedance recorded in reporting period. Noise monitoring results
measured in this reporting period are reviewed and summarized. Details of graphical presentation can be
referred in Appendix
4.1. 
Contract no. HY/2009/19  Central- Wan
Chai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link
4.1.7.
Noise
quality monitoring at M4b and M5b have been implemented with respect to
HY/2009/19 since the marine bore piling work started on 28 Jan 2012.
4.1.8.
The
proposed division of noise monitoring stations for Contract no. HY/2009/19 are
summarized in Table 4.4 below:
  Table 4.4   Noise Monitoring Stations for Contract no.  /span>HY/2009/19
Station |
Description |
M4b |
Victoria Centre |
M5b |
|
4.1.9.
There
was no exceedance recorded in reporting period. Noise monitoring results measured
in this reporting period are reviewed and summarized. Details of graphical presentation can be
referred in Appendix
4.1. 
4.2.1
No
construction activity was conducted during night time period (2300 to 0700) in
this reporting period.
Contract no.
HY/2009/11  Central  Wanchai Bypass, North Point Reclamation
4.2.2
The
proposed division of real time noise monitoring stations are summarized in Table
4.5 below. Real time noise monitoring for the filling works under
contract no. HY/2009/11 was commenced on 5 October 2010.
Table 4.5  Real Time Noise Monitoring
Station for Contract no. HY/2009/11
District |
Station |
Description |
Tin Hau |
RTN1 |
FEHD Hong Kong Transport Section
Whitefield Depot |
North Point |
RTN2 |
Oil Street Community Liaison
Centre |
4.2.3
Real time noise monitoring
results were reviewed and no project-related Action and Limit level exceedance
were recorded in the reporting period. Details of real time
noise monitoring results and graphical presentation can be referred to
Appendix 4.2
Contract no. HY/2009/19  Central- Wan
Chai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link
4.2.4
The
proposed division of real time noise monitoring stations are summarized in Table
4.6 below. Real time noise monitoring for the marine bored piling works
under contract no. HY/2009/19 was commenced on 28 January 2012.
Table 4.6  Real Time Noise Monitoring Station for Contract no. HY/2009/19
District |
Station |
Description |
Tin Hau |
RTN1 |
FEHD Hong Kong Transport Section
Whitefield Depot |
North Point |
RTN2 |
Oil Street Community Liaison
Centre |
4.2.5
Real time noise monitoring
results were reviewed and no project-related Action and Limit level exceedance
were recorded in the reporting period. Details of real time
noise monitoring results and graphical presentation can be referred to
Appendix 4.2
4.3.1.
Due to lack of electric supply, the 24-hr TSP
monitoring at the following stations were rescheduled as below:
CMA1b: from 4 January 2012 to 5 January
2012
       from 10 January 2012 to 11
January 2012
       from 20 January 2012 to 21
January 2012
       from 26 January 2012 to 27
January 2012
from 13 February 2012 to 16
February 2012
CMA3a: from 16 January 2012 to 17
January 2012
 /span>from 13 February 2012 to 14 February 2012
CMA5a: from 18 February 2012 to
20 February 2012
Contract no. HY/2009/11  Central  
Wanchai Bypass, North Point Reclamation
4.3.2.
The major work activities for Contract no.
HY/2009/11 was confirmed substantial complete by RSS on 4 January 2012. The
construction site was handed over to contractor HY/2009/19 and the FEP-01/356/2009
was under application of surrender in this reporting period. The monitoring for
the contract was temporary suspended on 6 January 2012.
4.3.3.
The proposed division of air monitoring stations is
summarized in Table 4.7 below.
Table 4.7  Air Monitoring Stations
for Contract no. HY/2009/11
Station |
Description |
CMA1b |
Oil Street Community Liaison Centre |
CMA2a |
|
4.3.4.
No
exceedance was recorded in the reporting period. Details of air monitoring
results and graphical presentation can be referred in
Appendix
4.2.
Contract no. HK/2009/01 - Wan Chai
Development Phase II  Central –Wanchai Bypass at HKCEC
4.3.5.
Air
monitoring was commenced on 1 April 2011 in response to the commencement of the
land-filling work for Contract no. HK/2009/01. The proposed division of air
monitoring stations are summarized in Table 4.8 
below. No exceedance was recorded in the reporting period.
Table 4.8   Air Monitoring Stations for Contract no. HK/2009/01
Station |
Description |
CMA5a |
Children Playgrounds opposite to |
CMA6a |
WDII PRE Site Office * |
Contract no. HK/2009/02 - Wan Chai
Development Phase II  Central  Wan Chai Bypass at WanChai East
4.3.6.
Air monitoring
was commenced in mid-January 2011 for the land-filling work for Contract no.
HK/2009/02. The proposed division of air monitoring stations is summarized in Table
4.9 below. No exceedance was recorded in the reporting period.
Table 4.9   Air Monitoring Station for
Contract no. HK/2009/02
Station |
Description |
CMA4a |
Society for the Prevention of Cruelty to Animals |
Contract no. HY/2009/15 - Central-Wanchai Bypass  Tunnel (
4.3.7.
Air
monitoring was commenced on 15 March 2011 for the land filling work for
Contract no. HY/2009/15.  /span>The proposed division of
air monitoring stations are summarized in Table 4.10 below. No
exceedance was recorded in the reporting period.
Table
4.10 Air Monitoring Station for Contract no. HY/2009/15
Station |
Description |
CMA3a |
CWB site office at Wanchai
Waterfront Promenade |
Contract no. HY/2009/19 –Central- Wan
Chai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link
4.3.8.
Air monitoring at CMA1b and CMA2a have been
implemented with respect to HY/2009/19 since the marine bore piling works
started on 28 Jan 12. No exceedance was recorded in the
reporting period.
4.3.9.
The proposed division of air monitoring stations is
summarized in Table 4.11 below.
Table 4.11 Air Monitoring Stations for Contract no. HY/2009/19
Station |
Description |
CMA1b |
Oil Street Community Liaison Centre |
CMA2a |
|
4.3.10.
The
odour patrol along the odour route with 8 sniffing locations was conducted by a
qualified odour patrol member. There was no odour patrol in this reporting
period.
Contract no. HY/2009/11  Central  
Wanchai Bypass, North Point Reclamation
4.4.1.
Water quality monitoring for Contract no.
HY/2009/11 was commenced on 19 March 2010. The proposed division of water
monitoring stations for Contract no. HY/2009/11 is summarized in Table
4.12 below:
Table
4.12 Water Monitoring Stations
for Contract no.  /span>HY/2009/11
Station
Ref. |
Location |
Easting |
Northing |
WSD Salt Water Intake |
|||
WSD9 |
Tai Wan |
837921.0 |
818330.0 |
WSD10 |
Cha Kwo Ling |
841900.9 |
817700.1 |
WSD15 |
Sai Wan Ho |
841110.4 |
816450.1 |
WSD17 |
|
839790.3 |
817032.2 |
Cooling Water Intake |
|||
C8 |
|
837970.6 |
816957.3 |
C9 |
Provident Garden |
838355.0 |
817116.6 |
      Remarks:
WSD9, WSD10, WSD15, WSD17. C8 and C9 water monitoring finished on 6 Feb 2012.
Contract no. HK/2009/01 - Wan Chai
Development Phase II  Central –Wanchai Bypass at HKCEC
4.4.2.
Water quality monitoring for Contract no.
HK/2009/01 was commenced on 23 July 2010. The proposed division of water
monitoring stations is summarized in Table 4.13 below.
Table 4.13 Water Monitoring Stations for Contract no. HK/2009/01
Station
Ref. |
Location |
Easting |
Northing |
WSD Salt Water Intake |
|||
WSD7 |
|
834150.0 |
818300.3 |
WSD19 |
Sheung Wan |
833415.0 |
816771.0 |
WSD20 |
|
830750.6 |
816030.3 |
Cooling Water Intake |
|||
C1 |
HKCEC
Extension |
835885.6 |
816223.0 |
C2 |
Telecom
House |
835647.9 |
815864.4 |
C3 |
HKCEC Phase
I |
835836.2 |
815910.0 |
C4e |
Wan |
835932.8 |
815888.2 |
C4w |
Wan |
835629.8 |
815889.2 |
Remarks:
The
water monitoring stations for the dredging works under Contract No. HK/2009/01
should also include WSD9, WSD17, WSD 21 and C5 if water quality monitoring at
these locations have not been carried out by others. Similarly, the water
monitoring stations for the dredging works under Contract No. HK/2009/02 should
also include WSD7, WSD9, WSD17, WSD 19, C1, C2, C3 and C4 if water quality
monitoring at these locations have not been carried out by others.
Contract no. HK/2009/02 - Wan Chai
Development Wan Chai Development Phase II  Central  Wan Chai Bypass at
WanChai East
4.4.3.
Water
quality monitoring for Contract no. HK/2009/02 was commenced on 8 July 2010.
The proposed division of water monitoring stations is summarized in Table
4.14 below.
Table 4.14 Water Monitoring Stations for Contract no. HK/2009/02
Station
Ref. |
Location |
Easting |
Northing |
|||
WSD Salt Water Intake |
||||||
WSD21 |
Wan Chai |
836220.8 |
815940.1 |
|||
WSD9 (Monitoring started from 8 Feb 12) |
Sheung Wan |
833415.0 |
816771.0 |
|||
WSD17 (Monitoring started from 8 Feb 12) |
|
830750.6 |
816030.3 |
|||
Cooling Water Intake |
||||||
C5e |
Sun Hung Kai
Centre (Eastern) |
836250.1 |
815932.2 |
|||
C5w |
Sun Hung Kai
Centre (Western) |
836248.1 |
815933.2 |
|||
Remarks:
-
The
water monitoring stations for the dredging works under Contract No. HK/2009/01
should also include WSD9, WSD17, WSD 21 and C5 if water quality monitoring at
these locations have not been carried out by others. Similarly, the water
monitoring stations for the dredging works under Contract No. HK/2009/02 should
also include WSD7, WSD9, WSD17, WSD 19, C1, C2, C3 and C4 if water quality
monitoring at these locations has not been carried out by others.
-
Water
quality monitoring at WSD9 and WSD 17 was implemented with respect to HK/2009/02
from 8 Feb 2012.
Contract no. HK/2010/06 - Wan Chai Development
Phase II  Central –Wanchai Bypass over MTR Tsuen Wan Line
4.4.4.
Water
monitoring for Contract no. HK/2010/06 was commenced on 8 March 2011. The
proposed division of water monitoring stations are summarized in Table
4.15 below.
Table
4.15 Water Monitoring Stations
for Contract no. HK/2010/06
Station
Ref. |
Location |
Easting |
Northing |
Cooling Water Intake |
|||
C2 |
Telecom
House |
835647.9 |
815864.4 |
Contract no.
HY/2009/15 - Central-Wanchai Bypass  Tunnel (
4.4.5.
Due to the commencement of the
maintenance dredging on 10 November 2010, water quality monitoring for Contract
no. HY/2009/15 was commenced on 9 November 2010. The proposed division of water
monitoring stations is summarized in Table 4.16 below.
Table
4.16 Water Monitoring Stations for Contract no.
HY/2009/15
Station
Ref. |
Location |
Easting |
Northing |
Cooling Water Intake |
|||
C6 |
Excelsior Hotel |
837009.6 |
815999.3 |
C7 |
|
837193.7 |
816150 |
Remarks: -    The cessation of seawater intake operation for C6
was confirmed on 17 May 2011, the water monitoring at C6 was then terminated
since 17 May 2011.
Contract no. HY/2009/19  Central- Wan
Chai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link
4.4.6.
Due to the commencement of the marine bored piling
on 28 Jan 2012, water quality monitoring for Contract no. HY/2009/19 was
commenced on 28 Jan 2012. The proposed division of water monitoring stations
are summarized in Table 4.17 below.
Table 4.17  Water
Monitoring Stations for Contract no. HY/2009/19
Station
Ref. |
Location |
Easting |
Northing |
Cooling Water Intake |
|||
C8 |
|
837970.6 |
816957.3 |
C9 |
Provident
Garden |
838355.0 |
817116.6 |
     Remarks: C8 and C9 water monitoring
commenced on 28 Jan 2012.
4.4.7.
The
enhanced water quality monitoring at C6, C7, Ex-WPCWA-SW and Ex-WPCWA-SE was
commenced on 13 January 2011.  /span>No
project-related exceedances was recorded in the daily SS monitoring and 24
hours turbidity monitoring.
4.4.8.
As
per the meeting with the representative of Excelsior Hotel and World Trade
Centre on 17 May 2011, they confirmed that the seawater intake for The
Excelsior was no longer in use and replaced by the connected permanent water
supply from WSD pipelines since 11 January 2011. Thus, the impact water quality
monitoring for the cooling intake - C6 was terminated effective from 26 May
2011. 
4.4.9.
24 hours monitoring of
turbidity at the cooling water intakes at C7 was conducted. With
respect to the seawall collapsing at TS4 on 17 November 2011, the 24 hours
turbidity monitoring and was kept in November 2011. Since the reinstating the
seawall was completed on 13 January 2012 and no any water deterioration was
performed, 24 hour turbidity monitoring was then suspended on 27 January 2012.
4.4.10.
Water
monitoring results measured in this reporting period are reviewed and
summarized in Table 4.18. Details of water quality
monitoring results and graphical presentation can be referred in
Appendix
4.3.
Table 4.18 Summary of Water Quality Monitoring Exceedances in Reporting period
Water
Monitoring Station |
Mid-flood |
Mid-ebb |
||||||||||||
DO |
Turbidity |
SS |
DO |
Turbidity |
SS |
|||||||||
|
LL |
|
LL |
|
LL |
|
LL |
|
LL |
|
LL |
|||
HY/2009/11 |
WSD9 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
Monitoring finished on 6 Feb 2012 |
WSD10 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
WSD15 |
0 |
0 |
0 |
0 |
0 |
1 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
WSD17 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
C8 |
0 |
0 |
2 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
1 |
0 |
|
|
C9 |
0 |
0 |
1 |
0 |
0 |
0 |
0 |
0 |
1 |
0 |
1 |
0 |
|
HK/2009/01 |
WSD19 |
0 |
0 |
0 |
1 |
1 |
1 |
0 |
0 |
1 |
0 |
0 |
1 |
|
|
WSD20 |
0 |
0 |
1 |
3 |
0 |
3 |
0 |
0 |
0 |
1 |
0 |
1 |
|
|
WSD7 |
0 |
0 |
1 |
1 |
0 |
2 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
C1 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
C3 |
0 |
0 |
0 |
0 |
2 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
C4e |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
1 |
|
|
C4w |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
1 |
|
HK/2009/01 & HK/2010/06 |
C2 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
HK/2009/02 |
C5e |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
1 |
0 |
1 |
0 |
|
|
C5w |
0 |
0 |
0 |
0 |
0 |
1 |
0 |
0 |
0 |
0 |
1 |
0 |
|
|
WSD21 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
1 |
|
Monitoring started on 8 Feb 2012 |
WSD9 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
Monitoring started on 8 Feb 2012 |
WSD17 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
HY/2009/15 |
C7 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
HY/2009/19 Monitoring started from 28 Jan 2012 |
C8 |
0 |
0 |
0 |
1 |
1 |
0 |
0 |
0 |
1 |
0 |
1 |
0 |
|
C9 |
0 |
0 |
0 |
1 |
1 |
0 |
0 |
0 |
0 |
0 |
1 |
0 |
||
Total |
0 |
0 |
5 |
7 |
5 |
8 |
0 |
0 |
4 |
1 |
6 |
5 |
||
Remarks: -    The cessation of
seawater intake operation for C6 was confirmed on 17 May 2011, the water
monitoring at C6 was then terminated since 17 May 2011.
         /span>-   /span>WSD9 and WSD17 were implemented with respect
to HK/2009/02 from 8 Feb 2012.
-  /span>4-week water quality monitoring at WSD9,
WSD10, WSD15, WSD17, C8 and C9 were completed on 6 Feb 2012.
-   /span>C8 and C9 were implemented with respect to
HY/2009/19 from 28 Jan 2012.
4.4.11.
Enhanced
DO monitoring at 4 monitoring stations in Causeway Bay Typhoon Shelter and
Ex-Public Cargo Works Area was conducted three days per week during the
reporting period. The action and limit level exceedances of water quality
monitoring are summarized in Table 4.18a.
Table 4.18a   Summary of Enhanced
Dissolved Oxygen Monitoring Exceedances in Reporting period
Contract no. |
Water Monitoring
Station |
Mid-flood |
Mid-ebb |
||
DO |
DO |
||||
|
LL |
|
LL |
||
C6 |
0 |
0 |
0 |
0 |
|
C7 |
0 |
0 |
0 |
0 |
|
Ex-WPCWA SW |
0 |
0 |
0 |
0 |
|
Ex-WPCWA SE |
0 |
1 |
0 |
0 |
|
Total |
0 |
1 |
0 |
0 |
4.4.12.
Investigations
were found that the exceedances are not related to the Project works. Water
monitoring results measured in this reporting period are reviewed and
summarized. Details of graphical
presentation can be referred in
Appendix 4.3.
Contract no. HY/2009/11  Central  
Wanchai Bypass, North Point Reclamation
4.5.1.
The major work activities for Contract no.
HY/2009/11 was confirmed substantial complete by RSS on 4 January 2012. Therefore,
no C&D waste was generated since 4 January 2012. Details of the waste flow
table are summarized in Table 4.19.
Table 4.19 Details of Waste Disposal for Contract no. HY/2009/11
Waste Type |
Quantity this quarter |
Cumulative Quantity-to-Date |
Disposal / Dumping Grounds |
Inert C&D materials disposed, m3 |
NIL |
NIL |
N/A |
Inert C&D materials recycled, m3 |
NIL |
NIL |
N/A |
Non-inert C&D materials disposed, m3 |
73.13 |
692.255 |
SENT Landfill |
Non-inert C&D materials recycled, m3 |
NIL |
NIL |
N/A |
Chemical waste disposed, kg |
N/A |
N/A |
N/A |
Marine Sediment (Type 1  Open Sea
Disposal), m3 |
0 (Bulk Volume) |
89,500 (Bulk Volume) |
South of Cheung Chau |
Marine Sediment (Type 1  Open Sea Disposal
(Dedicate Sites) & Type 2  Confined Marine Disposal), m3 |
0  /span>(Bulk
Volume) |
129,200  /span>(Bulk
Volume) |
East of Sha Chau |
4.5.2.
There
was no marine sediment disposed and no dredging work undertaken in the
reporting period. Contractor submitted a letter dated 20 July 2011 to confirm
that the dredging works and dumping operation were completed.
Contract no. HK/2009/01 - Wan Chai Development
Phase II  Central –Wanchai Bypass at HKCEC
4.5.3.
Inert and non-inert C&D waste was disposed of for the site
preparation works in this reporting period. Details of the waste flow table are
summarized in Table 4.20.
Table 4.20 Details of Waste Disposal for Contract no. HK/2009/01
Waste Type |
Quantity this quarter |
Cumulative Quantity-to-Date |
Disposal / Dumping Grounds |
Inert C&D materials disposed, m3 |
4667.56 |
16534.16 |
TKO137, TM38 |
Inert C&D materials recycled, m3 |
0 |
389.96 |
N/A |
Non-inert C&D materials disposed, m3 |
109.64 |
614.20 |
SENT Landfill |
Non-inert C&D materials recycled, kg |
8833 |
135,754 |
N/A |
Chemical waste disposed, kg |
530 |
5660 |
N/A |
Marine Sediment (Type 1  Open Sea Disposal)
, m3 |
0 |
83,482.2 (Bulk Volume) |
South of Cheung Chau |
Marine Sediment (Type 1  Open Sea Disposal
(Dedicate Sites) & Type 2  Confined Marine Disposal) , m3 |
5656 |
23386 (Bulk Volume) |
East of Cha Chau |
Dredged Sediment Requiring Type 3  Special Treatment / Disposal contained in
Geosynthetic Containers |
3660 |
3917 (Bulk Volume) |
East of Cha Chau |
4.5.4.
There
were marine sediments Type 1  Open Sea Disposal, Type 1  Open Sea Disposal
(Dedicate Sites) & Type 2  Confined Marine Disposal and Type 3  Special
Treatment / Disposal contained in Geosynthetic Containers disposed in the
reporting period. The maximum dredging rate in HKCEC3w and cross harbour water
main are 502m3 and 539m3 per day respectively, which were complied with the recommended maximum dredging rate per day
listed in Table 2 of FEP-02/356/2009.
Contract no. HK/2009/02 - Wan Chai Development
Phase II  Central  Wan Chai Bypass at WanChai East
4.5.5.
Inert and non-inert C&D waste was disposed of for the site
preparation works in this reporting period. Details of the waste flow table are
summarized in Table 4.21.
Table 4.21 Details of Waste Disposal for Contract no. HK/2009/02
Waste Type |
Quantity this quarter |
Cumulative Quantity-to-Date |
Disposal / Dumping Grounds |
Inert C&D materials disposed, m3 |
30329 |
84,065 |
TKO137/ TM 38 |
Inert C&D materials recycled, m3 |
NIL |
NIL |
N/A |
Non-inert C&D materials disposed, m3 |
90 |
349 |
SENT Landfill |
Non-inert C&D materials recycled, m3 |
NIL |
NIL |
N/A |
Chemical waste disposed, kg |
2071 |
4,186 |
N/A |
Marine Sediment (Type 1  Open Sea
Disposal), m3 |
332 (Bulk volume) |
154,827 (Bulk Volume) |
South of Cheung Chau |
Marine Sediment (Type 1  Open Sea Disposal
(Dedicate Sites) & Type 2  Confined Marine Disposal), m3 |
0 |
110,632 (Bulk Volume) |
East of Sha Chau |
4.5.6.
There
were marine sediments Type 1  Open Sea Disposal in the reporting period. The maximum
dredging rate in submarine sewage pipelines is 332 m3 per day, which
was complied with the recommended maximum dredging rate per day in sub-marine
pipeline work zone listed in Table 2 of FEP-03/356/2009.
Contract no. HY/2009/15 -
Central-Wanchai Bypass  Tunnel (
4.5.7.
Inert and non-inert C&D waste was disposed of for the site
preparation works in this reporting period. Details of the waste flow table are
summarized in Table 4.22.
Table 4.22 Details of Waste Disposal for Contract no. HY/2009/15
Waste Type |
Quantity this quarter |
Cumulative Quantity-to-Date |
Disposal / Dumping Grounds |
Inert C&D materials disposed, m3 |
59596.9 |
118145.2 |
Tuen Mun Area 38 |
384.9 |
951.2 |
TKO137 FB |
|
Inert C&D materials recycled, m3 |
0 |
184.0 |
To Contract HY/2009/11 |
0 |
304 |
Ex-PCWA |
|
|
0 |
109 |
TS4 |
Non-inert C&D materials disposed, m3 |
47 |
190.6 |
SENT Landfill |
Non-inert C&D materials recycled, kg |
150 |
13,965 |
N/A |
Chemical waste disposed, kg |
2,200 |
8,000 |
N/A |
Marine Sediment (Type 1  Open Sea Disposal)
, m3 |
0 |
33,427  /span>(Bulk
Volume) |
South of Cheung Chau |
Marine Sediment (Type 1  Open Sea Disposal
(Dedicate Sites) & Type 2  Confined Marine Disposal) , m3 |
0 |
158,812  /span>(Bulk
Volume) |
East of Sha Chau |
Marine Sediment (Type 3  Special Treatment
/ Disposal contained in Geosynthetic Containers) |
0 |
7,050 (Bulk Volume) |
East of Sha Chau |
4.5.8.
There
was no marine sediment disposed of in this reporting period.
Contract no.
HK/2010/06 - Wan Chai Development Phase II  Central –Wanchai Bypass over MTR
Tsuen Wan Line
4.5.9.
Inert C&D waste was disposed of for the site preparation works in this
reporting period. Details of the waste flow table are summarized in Table
4.23.
Table 4.23 Details of Waste Disposal for Contract no. HK/2010/06
Waste Type |
Quantity this month |
Cumulative Quantity-to-Date |
Disposal / Dumping Grounds |
Inert C&D materials disposed, m3 |
5860.33 |
9029.83 |
Tuen Mun Area 38 |
Inert C&D materials recycled, m3 |
NIL |
NIL |
N/A |
Non-inert C&D materials disposed, m3 |
NIL |
NIL |
N/A |
Non-inert C&D materials recycled, kg |
461.5 |
461.5 |
N/A |
Chemical waste disposed, L |
0 |
600 |
N/A |
Marine Sediment (Type 1  Open Sea Disposal), m3 |
640  /span>(Bulk
Volume) |
3,297 (Bulk Volume) |
South Cheung Chau |
Marine Sediment (Type 1  Open Sea Disposal
(Dedicate Sites) & Type 2  Confined Marine Disposal) , m3 |
788 (Bulk Volume) |
12,297 (Bulk Volume) |
|
4.5.10. There were marine sediments Type 1  
Open Sea Disposal and Type 1  Open Sea Disposal (Dedicate Sites) & Type 2
 Confined Marine Disposal dredging from bore-piling casing in the reporting
period.
Contract no. HY/2009/19
 Central- WanChai Bypass Tunnel (North Point Section) and Island Eastern
Corridor Link
4.5.11. There was no project-related waste
disposal in the reporting period.
5.0.1.
The
Event Action Plan for construction noise, air quality and water quality are
presented in Appendix 5.1.
5.1.1
Three limit level exceedances at M1a on 29
November, 6 December 2011 and 10 January 2012 during restricted hour in the reporting
period. Major noise source at M1a was contributed from
5.1.2
No Action levels was
recorded in this reporting period.
5.2.1
No
project-related exceedance was recorded in the real-time noise results in reporting
period.
5.3.1.
No
exceedance was recorded in the reporting period.
5.4.1.
The summary
of water quality exceedances recorded in reporting period is presented in the Table
5.1 and Table 5.1a.
Table 5.1  Summary of Water Quality Monitoring
Exceedances in Reporting period
Contract
no. |
Water
Monitoring Station |
Mid-flood |
Mid-ebb |
|||||||||||
DO |
Turbidity |
SS |
DO |
Turbidity |
SS |
|||||||||
|
LL |
|
LL |
|
LL |
|
LL |
|
LL |
|
LL |
|||
HY/2009/11 |
WSD9 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
Monitoring finished on 6 Feb 2012 |
WSD10 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
WSD15 |
0 |
0 |
0 |
0 |
0 |
1 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
WSD17 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
C8 |
0 |
0 |
2 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
1 |
0 |
|
|
C9 |
0 |
0 |
1 |
0 |
0 |
0 |
0 |
0 |
1 |
0 |
1 |
0 |
|
HK/2009/01 |
WSD19 |
0 |
0 |
0 |
1 |
1 |
1 |
0 |
0 |
1 |
0 |
0 |
1 |
|
|
WSD20 |
0 |
0 |
1 |
3 |
0 |
3 |
0 |
0 |
0 |
1 |
0 |
1 |
|
|
WSD7 |
0 |
0 |
1 |
1 |
0 |
2 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
C1 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
C3 |
0 |
0 |
0 |
0 |
2 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
C4e |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
1 |
|
|
C4w |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
1 |
|
HK/2009/01 & HK/2010/06 |
C2 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
HK/2009/02 |
C5e |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
1 |
0 |
1 |
0 |
|
|
C5w |
0 |
0 |
0 |
0 |
0 |
1 |
0 |
0 |
0 |
0 |
1 |
0 |
|
|
WSD21 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
1 |
|
Monitoring started on 8 Feb 2012 |
WSD9 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
Monitoring started on 8 Feb 2012 |
WSD17 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
HY/2009/15 |
C7 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
HY/2009/19 Monitoring started from 28 Jan 2012 |
C8 |
0 |
0 |
0 |
1 |
1 |
0 |
0 |
0 |
1 |
0 |
1 |
0 |
|
C9 |
0 |
0 |
0 |
1 |
1 |
0 |
0 |
0 |
0 |
0 |
1 |
0 |
||
Total |
0 |
0 |
5 |
7 |
5 |
8 |
0 |
0 |
4 |
1 |
6 |
5 |
||
Remarks: -    The cessation of seawater intake operation
for C6 was confirmed on 17 May 2011, the water monitoring at C6 was then
terminated since 17 May 2011.
         /span>-   /span>WSD9 and WSD17 were implemented with respect
to HK/2009/02 from 8 Feb 2012.
-  /span> /span>4-week water quality monitoring at WSD9,
WSD10, WSD15, WSD17, C8 and C9 were completed on 6 Feb 2012.
-   /span> /span>C8 and
C9 were implemented with respect to HY/2009/19 from 28 Jan 2012.
6.4.1.
All exceedances in Table 5.1 have been investigated and there was no project-related exceedance.
Table 5.1a    Summary of Enhanced Dissolved Oxygen
Monitoring Exceedances in Reporting period
Contract no. |
Water Monitoring Station |
Mid-flood |
Mid-ebb |
||
DO |
DO |
||||
|
LL |
|
LL |
||
HY/2009/15 |
C6 |
0 |
0 |
0 |
0 |
C7 |
0 |
0 |
0 |
0 |
|
Ex-WPCWA SW |
0 |
0 |
0 |
0 |
|
Ex-WPCWA SE |
0 |
1 |
0 |
0 |
|
Total |
0 |
1 |
0 |
0 |
5.4.2.
Investigation
was found that the exceedances was not related to the Project works.
5.5.1.
There
was no non-compliance from the site audits in the reporting period. During
environmental site inspections conducted during the reporting period, minor
deficiencies were noted.
5.6.1
There
was no non-compliance from the site audits in the reporting period.
6.0.1.
There
was no environmental complaint received in this reporting period.
6.0.2.
The details of cumulative complaint log and summary
of complaints are presented in
Appendix
6.1.
6.0.3.
No notification of summons
or prosecution was received in the reporting period. Cumulative statistic on complaints and successful
prosecutions are summarized in Table 6.1 and Table 6.2 respectively.
Table 6.1  Cumulative Statistics on Complaints
Reporting Period |
No. of Complaints |
Commencement works
(Mar 2010) to last reporting period |
25 |
Dec
2011- Feb 2012 |
0 |
Project-to-Date |
25 |
Table 6.2  Cumulative Statistics on Successful
Prosecutions
Environmental Parameters |
Cumulative No. Brought Forward |
No. of Successful Prosecutions this quarter (Offence Date) |
Cumulative No. Project-to-Date |
Air |
- |
0 |
0 |
Noise |
- |
0 |
0 |
Water |
- |
0 |
0 |
Waste |
- |
0 |
0 |
Total |
- |
0 |
0 |
7.0.1.
According to Condition 3.4 of the EP-356/2009,
this section addresses the relevant cumulative construction impact due to the
concurrent activities of the current projects including the Central
Reclamation, Central-WanChai Bypass and Island Eastern Corridor Link projects.
7.0.2.
According to the construction programme of Wan Chai
Development Phase II, Central-Wan Chai Bypass and Island Eastern Corridor Link
projects, the major construction activities at Reclamation Shoreline Sub-zones
under Wan Chai Development Phase II were the dredging and filling at HKCEC3w, dredging
at submarine sewage pipelines, seawall block construction at TCBR1W and marine
bored piling at MTR Tunnel Crossing in the reporting period. The major
environmental impact was water quality impact at North Point,
7.0.3.
The major environmental impacts generated from the
filling work at Central Reclamation Phase III were only located along the
coastline of Central and Admiralty while the adverse water impact was only located in the
HKCEC water channel in relation to the rock filling operation causing
exceedances in HKCEC water channel in this reporting period. Thus, it was
unlikely to have cumulative impact from CRIII. It is evaluated the cumulative
construction impact from the concurrent projects including Wan Chai Development
Phase II and Central Reclamation Phase III was insignificant.
8.0.1.
The
EM&A programme was carried out in accordance with the EM&A Manual
requirements, minor alterations to the programme proposed were made in response
to changing circumstances.
8.0.2.
No
non-compliances were noted and no prosecutions were received during the reporting
period.
8.0.3.
The
construction programmes of individual contracts are provided in
Appendix 7.1.